Bridge No. 57C0418 - GEORGIA ST & UNIVERSITY AVE

Description: Bridge No. 57C0418 - GEORGIA ST & UNIVERSITY AVE - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego County
City San Diego
Zip Code 92103
 
Senate District
39
Assembly District 76
Congressional District 53
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
San Diego Marnell Gibson (619) 533-5213   mgivson@sandiego.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$143 $0 $143
Non-bond Funding
State/Federal*
$2,344 $0 $2,344
Local**
$1,200 $0 $1,200
Private***
$0 $0 $0
 
Total**** $3,687 $0 $3,687

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$2,444 $0 $2,444 $2,257 $2,444 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,243 $0 $1,243 $0 $1,243 $0
 
Total* $3,687 $0 $3,687 $2,257 $3,687 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
12/01/2008 

07/01/2009 
 

 
12/01/2008 

07/01/2009 
100  12/01/2008 

07/01/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2009 

07/01/2012 
 

10/15/2009 
07/01/2009 

07/01/2012 
100  07/01/2009 

02/02/2015 


-32 
Begin Right of Way Phase

End Right of Way Phase
07/01/2012 

09/01/2012 
 

10/15/2009 
07/01/2012 

09/01/2012 
100  04/01/2013 

05/19/2015 
-9 

-33 
Begin Construction Phase

End Construction Phase
12/01/2012 

12/01/2013 
10/15/2009 

10/15/2009 
12/01/2012 

12/01/2013 
10/01/2015 

12/01/2016 
-34 

-37 
Begin Closeout Phase

End Closeout Phase
12/01/2014 

 
 

 
12/01/2014 

 
02/01/2017 

06/01/2017 
-26 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.