Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 58C0014 - FORRESTER ROAD & WESTSIDE MAIN CANAL |
Description: BRIDGE NO. 58C0014 - FORRESTER ROAD & WESTSIDE MAIN CANAL - BRIDGE SEISMIC RETROFIT
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Imperial County |
City | |
Zip Code | 92243 |
Senate District |
40 |
Assembly District | 80 |
Congressional District | 51 |
Caltrans District |
11 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Imperial County | Jose Castaneda | 4422651818 | josecastaneda@co.imperial.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$754 | $-643 | $111 | ||||
Non-bond Funding | |||||||
State/Federal* |
$5,822 | $2,291 | $8,113 | ||||
Local** |
$84 | $799 | $883 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $6,660 | $2,446 | $9,106 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$84 | $1,060 | $1,144 | $690 | $213 | $930 | |
Right of Way |
$250 | $1,750 | $2,000 | $0 | $250 | $1,750 | |
Construction |
$6,326 | $-363 | $5,963 | $0 | $5,347 | $616 | |
Total* | $6,660 | $2,446 | $9,106 | $690 | $5,810 | $3,296 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
02/28/2008 02/28/2009 |
|
02/28/2008 02/28/2009 |
100 | 03/01/2017 03/15/2021 |
-109 -147 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/28/2009 10/30/2011 |
|
03/01/2019 10/30/2022 |
75 | 03/15/2021 08/31/2023 |
-25 -10 |
Begin Right of Way Phase
End Right of Way Phase |
10/30/2010 10/30/2011 |
|
05/31/2022 08/31/2023 |
25 | 09/01/2021 11/30/2023 |
9 -3 |
Begin Construction Phase
End Construction Phase |
10/30/2011 04/30/2012 |
|
09/30/2023 08/31/2024 |
0 | 11/28/2024 06/30/2025 |
-14 -10 |
Begin Closeout Phase
End Closeout Phase |
|
|
12/31/2024 |
0 | 07/30/2025 07/30/2026 |
0 -19 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.