Bridge No. 58C0094 - WINTERHAVEN DRIVE & CALIFORNIA WASTEWAY |
Description: Bridge No. 58C0094 - WINTERHAVEN DRIVE & CALIFORNIA WASTEWAY - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Imperial County |
City | |
Zip Code | 92243 |
Senate District |
40 |
Assembly District | 80 |
Congressional District | 51 |
Caltrans District |
11 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Imperial County | Jose Castaneda | 442-265-1818 | josecastaneda@co.imperial.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$153 | $-57 | $95 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,179 | $-88 | $1,091 | ||||
Local** |
$18 | $28 | $46 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,350 | $-118 | $1,232 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$18 | $382 | $400 | $471 | $471 | $-71 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,332 | $-500 | $832 | $844 | $844 | $-12 | |
Total* | $1,350 | $-118 | $1,232 | $1,315 | $1,315 | $-83 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
10/30/2008 11/30/2009 |
|
10/30/2008 11/30/2009 |
100 | 11/21/2012 12/21/2013 |
-49 -49 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/30/2010 10/30/2011 |
10/15/2009 |
01/30/2010 03/21/2013 |
100 | 02/21/2015 04/21/2018 |
-62 -62 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | 04/08/2019 09/30/2019 |
0 0 |
Begin Construction Phase
End Construction Phase |
10/30/2011 06/30/2012 |
10/15/2009 10/15/2009 |
03/21/2013 11/21/2013 |
100 | 12/31/2018 03/15/2021 |
-70 -89 |
Begin Closeout Phase
End Closeout Phase |
12/30/2012 |
10/15/2009 |
08/21/2014 |
25 | 03/15/2021 10/30/2022 |
-80 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$152,780 |
Current Approved: |
$95,453 |
Actual Expenditures: |
$95,160 |
Status as of December 31, 2023.