Bridge No. 58C0094 - WINTERHAVEN DRIVE & CALIFORNIA WASTEWAY

Description: Bridge No. 58C0094 - WINTERHAVEN DRIVE & CALIFORNIA WASTEWAY - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Imperial County
City
Zip Code 92243
 
Senate District
40
Assembly District 80
Congressional District 51
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Imperial County Jose Castaneda 442-265-1818   josecastaneda@co.imperial.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$153 $-57 $95
Non-bond Funding
State/Federal*
$1,179 $-88 $1,091
Local**
$18 $28 $46
Private***
$0 $0 $0
 
Total**** $1,350 $-118 $1,232

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$18 $382 $400 $471 $471 $-71
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,332 $-500 $832 $844 $844 $-12
 
Total* $1,350 $-118 $1,232 $1,315 $1,315 $-83

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
10/30/2008 

11/30/2009 
 

 
10/30/2008 

11/30/2009 
100  11/21/2012 

12/21/2013 
-49 

-49 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/30/2010 

10/30/2011 
 

10/15/2009 
01/30/2010 

03/21/2013 
100  02/21/2015 

04/21/2018 
-62 

-62 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100  04/08/2019 

09/30/2019 


Begin Construction Phase

End Construction Phase
10/30/2011 

06/30/2012 
10/15/2009 

10/15/2009 
03/21/2013 

11/21/2013 
100  12/31/2018 

03/15/2021 
-70 

-89 
Begin Closeout Phase

End Closeout Phase
12/30/2012 

 
10/15/2009 

 
08/21/2014 

 
25  03/15/2021 

10/30/2022 
-80 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$152,780
Current Approved:
$95,453
Actual Expenditures:
$95,160

 

Status as of December 31, 2023.