Glen Helen Parkway Railroad Grade Separation

Description: Construct Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City
Zip Code 92407
 
Senate District
31, 32
Assembly District 63
Congressional District 26, 43
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated      1  
Rail/Highway At-Grade Crossings Eliminated  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
County of San Bernadino Robert Lopez (909) 387-8180   robert.lopez@dpw.sbcounty.gov
Design (PS&E) Phase
County of San Bernadino Robert Lopez (909) 387-8180   robert.lopez@dpw.sbcounty.gov
Right of Way Phase
County of San Bernadino Robert Lopez (909) 387-8180   robert.lopez@dpw.sbcounty.gov
Construction Phase
County of San Bernadino Robert Lopez (909) 387-8180   robert.lopez@dpw.sbcounty.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$7,172 $0 $7,172
Non-bond Funding
Local**
$19,696 $-3,053 $16,643
Private***
$0 $2,070 $2,070
 
Total**** $26,868 $-983 $25,885

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$2,650 $0 $2,650 $2,650 $2,650 $0
Right of Way
$3,000 $3,400 $6,400 $6,694 $6,694 $-294
Construction
$21,218 $-4,383 $16,835 $18,081 $18,081 $-1,246
 
Total* $26,868 $-983 $25,885 $27,425 $27,425 $-1,540

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2006 

06/30/2008 
 

01/20/2011 
06/01/2006 

04/30/2010 
100  06/01/2006 

04/19/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/01/2008 

09/30/2010 
01/20/2011 

01/08/2013 
04/01/2009 

12/01/2012 
100  04/01/2009 

12/01/2012 


Begin Right of Way Phase

End Right of Way Phase
11/01/2008 

09/01/2009 
01/20/2011 

01/08/2013 
04/01/2010 

12/18/2012 
100  04/20/2010 

04/15/2013 
-1 

-4 
Begin Construction Phase

End Construction Phase
11/01/2010 

11/01/2012 
01/08/2013 

01/08/2013 
04/05/2013 

08/22/2014 
100  05/07/2013 

05/18/2015 
-1 

-9 
Begin Closeout Phase

End Closeout Phase
11/01/2012 

06/01/2013 
01/08/2013 

 
09/01/2014 

03/01/2015 
100  05/19/2015 

08/21/2019 
-9 

-54 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1
Rail/Highway At-Grade Crossings Eliminated 1 1

Bond Funding Cost
Adopted:
$7,172,000
Current Approved:
$7,172,000
Actual Expenditures:
$7,172,000

 

Status as of December 31, 2023.