Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Glen Helen Parkway Railroad Grade Separation |
Description: Construct Grade Separation
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino |
City | |
Zip Code | 92407 |
Senate District |
31, 32 |
Assembly District | 63 |
Congressional District | 26, 43 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 | |
Rail/Highway At-Grade Crossings Eliminated | 1 | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
County of San Bernadino | Robert Lopez | (909) 387-8180 | robert.lopez@dpw.sbcounty.gov | |
Design (PS&E) Phase |
County of San Bernadino | Robert Lopez | (909) 387-8180 | robert.lopez@dpw.sbcounty.gov | |
Right of Way Phase |
County of San Bernadino | Robert Lopez | (909) 387-8180 | robert.lopez@dpw.sbcounty.gov | |
Construction Phase |
County of San Bernadino | Robert Lopez | (909) 387-8180 | robert.lopez@dpw.sbcounty.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$7,172 | $0 | $7,172 | ||||
Non-bond Funding | |||||||
Local** |
$19,696 | $-3,053 | $16,643 | ||||
Private*** |
$0 | $2,070 | $2,070 | ||||
Total**** | $26,868 | $-983 | $25,885 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$2,650 | $0 | $2,650 | $2,650 | $2,650 | $0 | |
Right of Way |
$3,000 | $3,400 | $6,400 | $6,694 | $6,694 | $-294 | |
Construction |
$21,218 | $-4,383 | $16,835 | $18,081 | $18,081 | $-1,246 | |
Total* | $26,868 | $-983 | $25,885 | $27,425 | $27,425 | $-1,540 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
06/01/2006 06/30/2008 |
01/20/2011 |
06/01/2006 04/30/2010 |
100 | 06/01/2006 04/19/2010 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
08/01/2008 09/30/2010 |
01/20/2011 01/08/2013 |
04/01/2009 12/01/2012 |
100 | 04/01/2009 12/01/2012 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
11/01/2008 09/01/2009 |
01/20/2011 01/08/2013 |
04/01/2010 12/18/2012 |
100 | 04/20/2010 04/15/2013 |
-1 -4 |
Begin Construction Phase
End Construction Phase |
11/01/2010 11/01/2012 |
01/08/2013 01/08/2013 |
04/05/2013 08/22/2014 |
100 | 05/07/2013 05/18/2015 |
-1 -9 |
Begin Closeout Phase
End Closeout Phase |
11/01/2012 06/01/2013 |
01/08/2013 |
09/01/2014 03/01/2015 |
100 | 05/19/2015 08/21/2019 |
-9 -54 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 | |
Rail/Highway At-Grade Crossings Eliminated | 1 | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$7,172,000 |
Current Approved: |
$7,172,000 |
Actual Expenditures: |
$7,172,000 |
Status as of December 31, 2023.