Caltrans Logo

Palm Avenue Railroad Grade Separation

Description: Construct Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City San Bernardino
Zip Code
 
Senate District
32
Assembly District 63
Congressional District 43
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated      1  
Rail/Highway At-Grade Crossings Eliminated  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
SANBAG Dennis Saylor (909) 884-8276   dsaylor@sanbag.ca.gov
Design (PS&E) Phase
SANBAG Dennis Saylor (909) 884-8276   dsaylor@sanbag.ca.gov
Right of Way Phase
SANBAG Dennis Saylor (909) 884-8276   dsaylor@sanbag.ca.gov
Construction Phase
SANBAG Dennis Saylor (909) 884-8276   dsaylor@sanbag.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$9,390 $-7,513 $1,877
Non-bond Funding
Local**
$25,786 $-12,793 $12,993
Private***
$0 $8,910 $8,910
 
Total**** $35,176 $-11,396 $23,780

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$750 $136 $886 $886 $886 $0
Design(PS&E)
$2,000 $2 $2,002 $2,002 $2,002 $0
Right of Way
$1,126 $8,518 $9,644 $9,643 $9,643 $1
Construction
$31,300 $-20,052 $11,248 $11,245 $11,245 $3
 
Total* $35,176 $-11,396 $23,780 $23,776 $23,776 $4

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2008 

12/30/2009 
 

01/08/2013 
07/01/2008 

07/31/2011 
100  07/01/2008 

07/11/2011 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2010 

06/30/2012 
 

01/08/2013 
01/01/2010 

01/15/2013 
100  01/01/2010 

03/31/2013 


-2 
Begin Right of Way Phase

End Right of Way Phase
07/01/2010 

06/30/2012 
01/08/2013 

01/08/2013 
09/24/2011 

02/11/2013 
100  07/12/2011 

03/31/2013 


-2 
Begin Construction Phase

End Construction Phase
07/01/2012 

12/30/2013 
01/08/2013 

01/08/2013 
06/01/2013 

06/30/2015 
100  09/01/2013 

09/11/2015 
-3 

-2 
Begin Closeout Phase

End Closeout Phase
01/01/2014 

06/30/2014 
01/08/2013 

 
07/01/2015 

09/01/2015 
100  09/11/2015 

02/16/2017 
-2 

-18 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1
Rail/Highway At-Grade Crossings Eliminated 1 1

Bond Funding Cost
Adopted:
$9,390,000
Current Approved:
$1,877,000
Actual Expenditures:
$1,877,000

 

Status as of December 31, 2023.