Lenwood Road Grade Separation

Description: Construct Grade Seapration

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City Barstow
Zip Code 92311
 
Senate District
18
Assembly District 34
Congressional District 25
 
Caltrans District
08
 
 
County/State Route San Bernardino 66
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated      1  
Rail/Highway At-Grade Crossings Eliminated  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Barstow Domingo Gonzales (760) 255-5156   dgonzales@barstowca.org
Design (PS&E) Phase
City of Barstow Domingo Gonzales (760) 255-5156   dgonzales@barstowca.org
Right of Way Phase
City of Barstow Domingo Gonzales (760) 255-5156   dgonzales@barstowca.org
Construction Phase
City of Barstow Domingo Gonzales (760) 255-5156   dgonzales@barstowca.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$6,694 $617 $7,311
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$18,381 $1,928 $20,309
Private***
$0 $975 $975
 
Total**** $25,075 $3,520 $28,595

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$2,760 $1,204 $3,964 $3,963 $3,963 $1
Right of Way
$743 $3,785 $4,528 $4,468 $4,468 $60
Construction
$21,572 $-1,469 $20,103 $20,102 $20,102 $1
 
Total* $25,075 $3,520 $28,595 $28,533 $28,533 $62

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/2008 

10/01/2010 
 

10/24/2012 
10/01/2008 

07/28/2011 
100  06/15/2009 

09/10/2011 
-8 

-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2011 

01/01/2012 
10/24/2012 

05/07/2013 
08/19/2010 

03/06/2013 
100  08/19/2010 

05/30/2013 


-3 
Begin Right of Way Phase

End Right of Way Phase
10/01/2010 

12/01/2011 
10/24/2012 

10/24/2012 
07/28/2011 

04/19/2013 
100  07/28/2011 

07/20/2014 


-15 
Begin Construction Phase

End Construction Phase
04/01/2012 

09/01/2013 
05/07/2013 

05/07/2013 
09/13/2013 

10/01/2015 
100  12/04/2013 

09/18/2015 
-3 

Begin Closeout Phase

End Closeout Phase
09/01/2013 

12/01/2013 
05/07/2013 

 
11/01/2015 

05/01/2016 
100  09/21/2015 

12/31/2017 


-20 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1
Rail/Highway At-Grade Crossings Eliminated 1 1

Bond Funding Cost
Adopted:
$6,694,000
Current Approved:
$7,311,000
Actual Expenditures:
$7,310,475

 

Status as of December 31, 2023.