Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
US 101 Rice Avenue Interchange |
Description: Reconstruct Interchange
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Ventura |
City | Oxnard |
Zip Code | |
Senate District |
23 |
Assembly District | 35, 41 |
Congressional District | 26 |
Caltrans District |
07 |
County/State Route | Ventura 101 |
Postmile Begin/End | 31.2 33.2 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 1 | |
Modified or Improved Interchanges (Nbr Modified) | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Oxnard | Cynthia Daniels | (805) 385-7871 | Cynthia.Daniels@oxnard.org | |
Design (PS&E) Phase |
City of Oxnard | Cynthia Daniels | (805) 385-7871 | Cynthia.Daniels@oxnard.org | |
Right of Way Phase |
City of Oxnard | Cynthia Daniels | (805) 385-7871 | Cynthia.Daniels@oxnard.org | |
Construction Phase |
City of Oxnard | Ashley Golden | (805) 385-7868 | ashley.golden@oxnard.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$30,449 | $-16,255 | $14,194 | ||||
Non-bond Funding | |||||||
Local** |
$56,450 | $-2,047 | $54,403 | ||||
Total**** | $86,899 | $-18,302 | $68,597 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$1,226 | $2,232 | $3,458 | $0 | $0 | $3,458 | |
Design(PS&E) |
$3,253 | $513 | $3,766 | $0 | $0 | $3,766 | |
Right of Way |
$21,522 | $5,072 | $26,594 | $0 | $0 | $26,594 | |
Construction |
$60,898 | $-21,119 | $39,779 | $45,056 | $0 | $39,779 | |
Total* | $86,899 | $-18,302 | $68,597 | $39,929 | $0 | $68,597 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
06/01/1999 02/26/2002 |
08/28/2008 08/28/2008 |
06/01/1999 02/26/2002 |
100 | 06/01/1999 03/26/2002 |
0 -1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/01/2002 08/30/2008 |
08/28/2008 08/28/2008 |
04/01/2002 08/30/2008 |
100 | 04/01/2002 05/06/2009 |
0 -8 |
Begin Right of Way Phase
End Right of Way Phase |
02/27/2002 08/30/2008 |
08/28/2008 02/22/2012 |
02/27/2002 05/05/2009 |
100 | 02/27/2002 05/05/2009 |
0 0 |
Begin Construction Phase
End Construction Phase |
03/01/2009 09/30/2011 |
02/22/2012 02/22/2012 |
10/20/2009 09/30/2012 |
100 | 10/20/2009 02/02/2016 |
0 -41 |
Begin Closeout Phase
End Closeout Phase |
10/30/2011 12/31/2011 |
02/22/2012 |
10/30/2012 12/31/2012 |
50 | 01/21/2016 04/20/2016 |
-39 -40 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 1 | |
Modified or Improved Interchanges (Nbr Modified) | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$30,449,000 |
Current Approved: |
$14,194,000 |
Actual Expenditures: |
$14,194,000 |
Status as of December 31, 2023.