Caltrans Logo

US 101 Rice Avenue Interchange

Description: Reconstruct Interchange

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Ventura
City Oxnard
Zip Code
 
Senate District
23
Assembly District 35, 41
Congressional District 26
 
Caltrans District
07
 
 
County/State Route Ventura 101
Postmile Begin/End 31.2 33.2
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (Mixed)  1      
Modified or Improved Interchanges (Nbr Modified)  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Oxnard Cynthia Daniels (805) 385-7871   Cynthia.Daniels@oxnard.org
Design (PS&E) Phase
City of Oxnard Cynthia Daniels (805) 385-7871   Cynthia.Daniels@oxnard.org
Right of Way Phase
City of Oxnard Cynthia Daniels (805) 385-7871   Cynthia.Daniels@oxnard.org
Construction Phase
City of Oxnard Ashley Golden (805) 385-7868   ashley.golden@oxnard.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$30,449 $-16,255 $14,194
Non-bond Funding
Local**
$56,450 $-2,047 $54,403
 
Total**** $86,899 $-18,302 $68,597

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1,226 $2,232 $3,458 $0 $0 $3,458
Design(PS&E)
$3,253 $513 $3,766 $0 $0 $3,766
Right of Way
$21,522 $5,072 $26,594 $0 $0 $26,594
Construction
$60,898 $-21,119 $39,779 $45,056 $0 $39,779
 
Total* $86,899 $-18,302 $68,597 $39,929 $0 $68,597

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/1999 

02/26/2002 
08/28/2008 

08/28/2008 
06/01/1999 

02/26/2002 
100  06/01/1999 

03/26/2002 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2002 

08/30/2008 
08/28/2008 

08/28/2008 
04/01/2002 

08/30/2008 
100  04/01/2002 

05/06/2009 


-8 
Begin Right of Way Phase

End Right of Way Phase
02/27/2002 

08/30/2008 
08/28/2008 

02/22/2012 
02/27/2002 

05/05/2009 
100  02/27/2002 

05/05/2009 


Begin Construction Phase

End Construction Phase
03/01/2009 

09/30/2011 
02/22/2012 

02/22/2012 
10/20/2009 

09/30/2012 
100  10/20/2009 

02/02/2016 


-41 
Begin Closeout Phase

End Closeout Phase
10/30/2011 

12/31/2011 
02/22/2012 

 
10/30/2012 

12/31/2012 
50  01/21/2016 

04/20/2016 
-39 

-40 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (Mixed) 1
Modified or Improved Interchanges (Nbr Modified) 1

Bond Funding Cost
Adopted:
$30,449,000
Current Approved:
$14,194,000
Actual Expenditures:
$14,194,000

 

Status as of December 31, 2023.