State Route 905

Description: Construct 6 Miles of 6 Lane Freeway and Extension to Existing Freeway

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego
City
Zip Code
 
Senate District
40
Assembly District 79
Congressional District 51
 
Caltrans District
11
 
 
County/State Route San Diego 905
Postmile Begin/End 5 10
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (Mixed)  20      
New Interchanges (Nbr Constructed)  2      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Ismael Salazar (619) 688-6766   Ismael_Salazar@dot.ca.gov
Design (PS&E) Phase
Caltrans Ismael Salazar (619) 688-6766   Ismael_Salazar@dot.ca.gov
Right of Way Phase
Caltrans Ismael Salazar (619) 688-6766   Ismael_Salazar@dot.ca.gov
Construction Phase
Caltrans Ismael Salazar (619) 688-6766   Ismael_Salazar@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$91,605 $-24,801 $66,804
Non-bond Funding
Local**
$13,095 $-4,513 $8,582
 
Total**** $104,700 $-29,314 $75,386

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$500 $-1 $499 $0 $0 $499
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$104,200 $-21,746 $82,454 $71,373 $0 $82,454
 
Total* $104,700 $-29,314 $75,386 $71,373 $0 $75,386

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

07/30/2004 
 

08/28/2008 
 

07/30/2004 
100   

07/30/2004 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/15/2008 

12/30/2008 
08/28/2008 

08/28/2008 
04/15/2008 

12/30/2008 
100  04/15/2008 

10/20/2008 


Begin Right of Way Phase

End Right of Way Phase
07/30/2004 

12/30/2008 
08/28/2008 

08/28/2008 
07/30/2004 

12/30/2008 
100  07/30/2004 

10/20/2008 


Begin Construction Phase

End Construction Phase
07/13/2009 

07/11/2012 
08/28/2008 

08/28/2008 
07/13/2009 

07/11/2012 
100  07/22/2009 

10/04/2013 


-15 
Begin Closeout Phase

End Closeout Phase
07/12/2012 

07/12/2013 
08/28/2008 

 
07/12/2012 

07/12/2013 
50  10/05/2013 

12/31/2014 
-15 

-18 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (Mixed) 20
New Interchanges (Nbr Constructed) 2

Bond Funding Cost
Adopted:
$91,605,000
Current Approved:
$74,371,000
Actual Expenditures:
$71,373,000

 

Status as of December 31, 2023.