Caltrans Logo

State Route 11 and Otay Mesa East Port of Entry

Description: Construct New 4 Lane Highway, 3 Connector Ramps for the State Route125 and State Route 905 Interchange and a New Otay Mesa East Port of Entry

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Diego
City Chula Vista, National City, San Diego
Zip Code
 
Senate District
40
Assembly District 79
Congressional District 51
 
Caltrans District
11
 
 
County/State Route San Diego 11
Postmile Begin/End 0 2.7
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (Mixed)  10      
New Interchanges (Nbr Constructed)  2      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Mark Baza (619) 688-2545   mark.baza@dot.ca.gov
Design (PS&E) Phase
Caltrans Mark Baza (619) 688-2545   mark.baza@dot.ca.gov
Right of Way Phase
Caltrans Mark Baza (619) 688-2545   mark.baza@dot.ca.gov
Construction Phase
Caltrans Mark Baza (619) 688-2545   mark.baza@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$75,000 $-845 $74,155
Non-bond Funding
State/Federal*
$6,600 $180 $6,780
Local**
$627,220 $-22,262 $604,958
 
Total**** $708,820 $-22,927 $685,893

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$7,400 $5,080 $12,480 $0 $0 $12,480
Design(PS&E)
$42,690 $1,021 $43,711 $0 $0 $43,711
Right of Way
$80,380 $31,003 $111,383 $0 $0 $111,383
Construction
$578,350 $-60,031 $518,319 $0 $0 $518,319
 
Total* $708,820 $-22,927 $685,893 $0 $0 $685,893

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/09/2007 

03/31/2010 
 

01/25/2012 
05/09/2007 

04/30/2012 
100  05/09/2007 

04/01/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2010 

12/31/2012 
 

01/25/2012 
04/01/2010 

07/31/2013 
40  04/01/2010 

07/31/2013 


Begin Right of Way Phase

End Right of Way Phase
01/01/2010 

12/31/2012 
01/13/2010 

01/25/2012 
01/01/2011 

07/31/2013 
01/01/2011 

07/31/2013 


Begin Construction Phase

End Construction Phase
04/01/2013 

03/31/2016 
01/25/2012 

01/25/2012 
07/15/2013 

06/30/2016 
40  10/02/2013 

12/23/2021 
-3 

-67 
Begin Closeout Phase

End Closeout Phase
04/01/2016 

04/01/2018 
01/25/2012 

 
04/01/2016 

10/30/2018 
12/23/2021 

02/23/2022 
-70 

-40 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (Mixed) 10
New Interchanges (Nbr Constructed) 2

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.