10th Avenue at Harbor Drive Grade Separation Improvements

Description: Construct at-grade improvements

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego
City San Diego
Zip Code
 
Senate District
40
Assembly District 79
Congressional District 51
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated      1  
Rail/Highway At-Grade Crossings Eliminated  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Mario Orso (619) 688-2561   mario_orso@dot.ca.gov
Design (PS&E) Phase
San Diego Unified Port District Mario Orso (619) 688-2561   mario_orso@dot.ca.gov
Right of Way Phase
San Diego Unified Port District Mario Orso (619) 688-2561   mario_orso@dot.ca.gov
Construction Phase
SANDAG Mario Orso (619) 688-2561   mario_orso@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$30,910 $-30,312 $598
Non-bond Funding
Local**
$36,290 $-32,934 $3,356
 
Total**** $67,200 $-63,246 $3,954

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$2,150 $-987 $1,163 $1,163 $1,163 $0
Design(PS&E)
$3,760 $-2,729 $1,031 $1,031 $1,031 $0
Right of Way
$8,990 $-8,990 $0 $0 $0 $0
Construction
$52,300 $-50,540 $1,760 $1,759 $1,759 $1
 
Total* $67,200 $-63,246 $3,954 $3,953 $3,953 $1

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/02/2008 

04/19/2011 
 

09/27/2012 
07/02/2008 

09/29/2011 
100  11/07/2008 

09/29/2011 
-4 

Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/20/2011 

05/23/2013 
09/27/2012 

 
09/30/2011 

05/23/2013 
100  10/04/2011 

05/23/2013 


Begin Right of Way Phase

End Right of Way Phase
04/20/2011 

05/23/2013 
09/27/2012 

 
09/30/2011 

05/23/2013 
100  04/20/2011 

05/23/2013 


Begin Construction Phase

End Construction Phase
11/07/2013 

08/25/2016 
 

 
11/07/2013 

08/25/2016 
100  10/04/2013 

01/15/2015 


20 
Begin Closeout Phase

End Closeout Phase
02/27/2017 

08/25/2017 
 

 
02/27/2017 

08/25/2017 
100  01/03/2017 

05/01/2017 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1
Rail/Highway At-Grade Crossings Eliminated 1

Bond Funding Cost
Adopted:
$30,910,000
Current Approved:
$598,000
Actual Expenditures:
$597,225

 

Status as of December 31, 2023.