Southline Rail Improvements (San Ysidro Yard Expansion Project)

Description: Track Addition

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego
City San Ysidro
Zip Code
 
Senate District
40
Assembly District 79
Congressional District 51
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Nbr Terminals Modified  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
SANDAG Pete d'Ablaing (619) 699-1906   pda@sandag.org
Design (PS&E) Phase
SANDAG Pete d'Ablaing (619) 699-1906   pda@sandag.org
Right of Way Phase
SANDAG Pete d'Ablaing (619) 699-1906   pda@sandag.org
Construction Phase
SANDAG Pete d'Ablaing (619) 699-1906   pda@sandag.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$25,900 $0 $25,900
Non-bond Funding
State/Federal*
$9,300 $-8,700 $600
Local**
$5,260 $8,700 $13,960
 
Total**** $40,460 $0 $40,460

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$540 $0 $540 $540 $540 $0
Design(PS&E)
$1,810 $672 $2,482 $2,817 $2,817 $-335
Right of Way
$12,210 $-5,340 $6,870 $4,023 $4,023 $2,847
Construction
$25,900 $4,668 $30,568 $31,970 $31,970 $-1,402
 
Total* $40,460 $0 $40,460 $39,350 $39,350 $1,110

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/05/2009 

01/01/2011 
 

 
01/05/2009 

01/01/2011 
100   

04/30/2011 


-4 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/05/2011 

07/01/2012 
 

 
01/05/2011 

07/01/2012 
100   

07/01/2012 


Begin Right of Way Phase

End Right of Way Phase
07/02/2010 

07/01/2012 
 

 
07/02/2010 

07/01/2012 
100   

12/03/2012 


-5 
Begin Construction Phase

End Construction Phase
01/04/2013 

01/01/2015 
 

 
01/04/2013 

01/01/2015 
100  01/04/2013 

07/31/2016 


-19 
Begin Closeout Phase

End Closeout Phase
01/02/2015 

04/02/2015 
 

 
01/02/2015 

04/02/2015 
100  01/02/2015 

01/31/2017 


-22 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Nbr Terminals Modified 1 1

Bond Funding Cost
Adopted:
$25,900,000
Current Approved:
$25,900,000
Actual Expenditures:
$25,900,000

 

Status as of December 31, 2023.