Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Southline Rail Improvements (San Ysidro Yard Expansion Project) |
Description: Track Addition
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Diego |
City | San Ysidro |
Zip Code | |
Senate District |
40 |
Assembly District | 79 |
Congressional District | 51 |
Caltrans District |
11 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Nbr Terminals Modified | 1 | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
SANDAG | Pete d'Ablaing | (619) 699-1906 | pda@sandag.org | |
Design (PS&E) Phase |
SANDAG | Pete d'Ablaing | (619) 699-1906 | pda@sandag.org | |
Right of Way Phase |
SANDAG | Pete d'Ablaing | (619) 699-1906 | pda@sandag.org | |
Construction Phase |
SANDAG | Pete d'Ablaing | (619) 699-1906 | pda@sandag.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$25,900 | $0 | $25,900 | ||||
Non-bond Funding | |||||||
State/Federal* |
$9,300 | $-8,700 | $600 | ||||
Local** |
$5,260 | $8,700 | $13,960 | ||||
Total**** | $40,460 | $0 | $40,460 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$540 | $0 | $540 | $540 | $540 | $0 | |
Design(PS&E) |
$1,810 | $672 | $2,482 | $2,817 | $2,817 | $-335 | |
Right of Way |
$12,210 | $-5,340 | $6,870 | $4,023 | $4,023 | $2,847 | |
Construction |
$25,900 | $4,668 | $30,568 | $31,970 | $31,970 | $-1,402 | |
Total* | $40,460 | $0 | $40,460 | $39,350 | $39,350 | $1,110 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/05/2009 01/01/2011 |
|
01/05/2009 01/01/2011 |
100 | 04/30/2011 |
0 -4 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/05/2011 07/01/2012 |
|
01/05/2011 07/01/2012 |
100 | 07/01/2012 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
07/02/2010 07/01/2012 |
|
07/02/2010 07/01/2012 |
100 | 12/03/2012 |
0 -5 |
Begin Construction Phase
End Construction Phase |
01/04/2013 01/01/2015 |
|
01/04/2013 01/01/2015 |
100 | 01/04/2013 07/31/2016 |
0 -19 |
Begin Closeout Phase
End Closeout Phase |
01/02/2015 04/02/2015 |
|
01/02/2015 04/02/2015 |
100 | 01/02/2015 01/31/2017 |
0 -22 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Nbr Terminals Modified | 1 | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$25,900,000 |
Current Approved: |
$25,900,000 |
Actual Expenditures: |
$25,900,000 |
Status as of December 31, 2023.