Caltrans Logo

BART 2

Description: R-Line North Aerials over public roads (28 Bridges). Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda County, Contra Costa County
City
Zip Code 94604
 
Senate District
03, 07, 08, 09, 10
Assembly District 09, 11, 12, 13, 14, 16, 19, 20
Congressional District 07, 08, 09, 10, 12, 13, 14
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Kenneth A. Duron (510) 464-6080   Boardof Directors@bart.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$1,418 $-826 $591
Non-bond Funding
State/Federal*
$10,943 $-6,378 $4,565
Local**
$0 $0 $0
Private***
$0 $0 $0
 
Total**** $12,361 $-7,204 $5,157

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$12,361 $-7,204 $5,157 $4,374 $4,374 $782
 
Total* $12,361 $-7,204 $5,157 $4,374 $4,374 $782

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

 
 

 
 

04/30/2007 
100   

04/30/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

03/10/2011 
100   

03/10/2011 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

07/30/2010 
100   

07/30/2010 


Begin Construction Phase

End Construction Phase
09/30/2009 

09/30/2013 
04/15/2011 

 
03/31/2012 

09/30/2013 
100  06/26/2011 

04/30/2014 


-7 
Begin Closeout Phase

End Closeout Phase
03/30/2014 

 
 

 
03/30/2014 

 
100  04/30/2014 

03/30/2015 
-1 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$1,417,879
Current Approved:
$591,488
Actual Expenditures:
$591,485

 

Status as of December 31, 2023.