Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
BRIDGE NO. 33C0321 - WEST OAKLAND PIER 110 TO TRANSBAY TUBE PORTAL |
Description: BRIDGE NO. 33C0321 - WEST OAKLAND PIER 110 TO TRANSBAY TUBE PORTAL
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Alameda County |
City | |
Zip Code | 94604 |
Senate District |
03, 07, 08, 09, 10 |
Assembly District | 09, 11, 12, 13, 14, 16, 19, 20 |
Congressional District | 07, 08, 09, 10, 12, 13, 14 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Kenneth A. Duron | (510) 464-6080 | Boardsof Directors@bart.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$193 | $-67 | $125 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,486 | $-520 | $966 | ||||
Local** |
$0 | $0 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,679 | $-587 | $1,091 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,679 | $-587 | $1,091 | $1,082 | $1,082 | $10 | |
Total* | $1,679 | $-587 | $1,091 | $1,082 | $1,082 | $10 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
|
|
|
100 | 04/14/2006 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
11/30/2009 |
|
11/30/2009 |
100 | 10/04/2010 |
0 -10 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | 06/30/2010 |
0 0 |
Begin Construction Phase
End Construction Phase |
09/30/2009 09/30/2013 |
|
09/30/2009 09/30/2013 |
100 | 03/14/2011 09/30/2013 |
-18 0 |
Begin Closeout Phase
End Closeout Phase |
|
|
|
100 | 03/30/2014 12/30/2014 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$192,581 |
Current Approved: |
$125,179 |
Actual Expenditures: |
$124,085 |
Status as of December 31, 2023.