BRIDGE NO. 33C0321 - WEST OAKLAND PIER 110 TO TRANSBAY TUBE PORTAL

Description: BRIDGE NO. 33C0321 - WEST OAKLAND PIER 110 TO TRANSBAY TUBE PORTAL

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda County
City
Zip Code 94604
 
Senate District
03, 07, 08, 09, 10
Assembly District 09, 11, 12, 13, 14, 16, 19, 20
Congressional District 07, 08, 09, 10, 12, 13, 14
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Kenneth A. Duron (510) 464-6080   Boardsof Directors@bart.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$193 $-67 $125
Non-bond Funding
State/Federal*
$1,486 $-520 $966
Local**
$0 $0 $0
Private***
$0 $0 $0
 
Total**** $1,679 $-587 $1,091

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,679 $-587 $1,091 $1,082 $1,082 $10
 
Total* $1,679 $-587 $1,091 $1,082 $1,082 $10

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

 
 

 
 

 
100   

04/14/2006 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

11/30/2009 
 

 
 

11/30/2009 
100   

10/04/2010 


-10 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

06/30/2010 


Begin Construction Phase

End Construction Phase
09/30/2009 

09/30/2013 
 

 
09/30/2009 

09/30/2013 
100  03/14/2011 

09/30/2013 
-18 

Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
100  03/30/2014 

12/30/2014 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$192,581
Current Approved:
$125,179
Actual Expenditures:
$124,085

 

Status as of December 31, 2023.