Bridge No. 01CA0002 - W/B I-80 on-ramp West of Yerba Buena Island

Description: BRIDGE NO. 01CA0002 - W/B I-80 ON-RAMP WEST OF YERBA BUENA ISLAND

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Francisco County
City San Francisco
Zip Code 94130
 
Senate District
03
Assembly District 13
Congressional District 08
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
San Francisco County Transportation Authority Lily Yu 415-522-4811   lily.yu@sfcta.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$874 $3,240 $4,114
Non-bond Funding
State/Federal*
$7,948 $37,021 $44,968
Local**
$156 $198 $354
Private***
$0 $0 $0
 
Total**** $8,977 $40,459 $49,436

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$1,360 $12,209 $13,569 $15,741 $15,741 $-2,172
Right of Way
$0 $713 $713 $595 $595 $119
Construction
$7,617 $27,537 $35,154 $7,362 $67,393 $-32,239
 
Total* $8,977 $40,459 $49,436 $23,698 $83,728 $-34,292

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
10/01/2010 

03/16/2011 
 

 
10/01/2010 

03/16/2011 
100  11/01/2010 

09/30/2011 
-1 

-7 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/24/2011 

07/04/2012 
 

 
08/30/2010 

10/31/2021 
100  09/30/2011 

02/23/2023 
-13 

-16 
Begin Right of Way Phase

End Right of Way Phase
07/01/2011 

11/30/2011 
 

 
04/30/2013 

10/31/2021 
100  09/30/2011 

12/31/2021 
19 

-2 
Begin Construction Phase

End Construction Phase
07/05/2012 

12/31/2013 
 

 
09/30/2022 

04/30/2026 
13  04/27/2023 

12/31/2026 
-7 

-8 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

04/30/2027 
01/01/2027 

12/31/2027 


-8 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.