Caltrans Logo

LOSSAN North Rail Corridor (Sorrento to Miramar Double Track Project) Phase I

Description: Add 1.2 Miles of a New Second Main Track

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego
City San Diego
Zip Code
 
Senate District
39
Assembly District 76
Congressional District 50
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Additional Track Miles Layed  1.2    1.4  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
SANDAG Pete D'Ablaing (619) 699-1906   pda@sandag.org
Design (PS&E) Phase
SANDAG Pete D'Ablaing (619) 699-1906   pda@sandag.org
Right of Way Phase
SANDAG Pete D'Ablaing (619) 699-1906   pda@sandag.org
Construction Phase
SANDAG Pete D'Ablaing (619) 699-1906   pda@sandag.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$10,800 $0 $10,800
Non-bond Funding
State/Federal*
$2,100 $1,100 $3,200
Local**
$10,800 $14,200 $25,000
 
Total**** $23,700 $15,300 $39,000

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1,600 $-1,600 $0 $0 $0 $0
Design(PS&E)
$500 $2,700 $3,200 $0 $0 $3,200
Right of Way
$600 $-600 $0 $0 $0 $0
Construction
$21,000 $14,800 $35,800 $0 $0 $35,800
 
Total* $23,700 $15,300 $39,000 $0 $0 $39,000

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
11/01/2008 

12/01/2009 
 

 
11/01/2008 

12/01/2009 
100  11/01/2008 

11/12/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2010 

03/01/2011 
 

05/11/2011 
01/01/2010 

04/30/2011 
100  01/01/2010 

05/01/2011 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2011 

09/01/2013 
 

05/11/2011 
09/01/2011 

09/30/2014 
100  08/19/2011 

07/08/2014 


Begin Closeout Phase

End Closeout Phase
10/01/2013 

04/01/2014 
05/11/2011 

 
10/30/2014 

10/13/2015 
100  07/08/2014 

09/23/2014 


13 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Additional Track Miles Layed 1.2 1.4

Bond Funding Cost
Adopted:
$10,800,000
Current Approved:
$10,800,000
Actual Expenditures:
$10,800,000

 

Status as of December 31, 2023.