Caltrans Logo

Sperry Road Extension Project

Description: Extend Sperry Road

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Stockton
Zip Code 95202
 
Senate District
05
Assembly District 17
Congressional District 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (Mixed)  4    1.0  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Stockton Wes Johnson (209) 937-8088   wes.johnson@stocktongov.com
Design (PS&E) Phase
City of Stockton Wes Johnson (209) 937-8088   wes.johnson@stocktongov.com
Right of Way Phase
City of Stockton Wes Johnson (209) 937-8088   wes.johnson@stocktongov.com
Construction Phase
City of Stockton James Wong (209) 937-8110   james.wong@stocktongov.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$30,000 $-6,418 $23,582
Non-bond Funding
Local**
$33,000 $0 $33,000
 
Total**** $63,000 $-6,418 $56,582

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1,000 $0 $1,000 $1,000 $1,000 $0
Design(PS&E)
$5,000 $0 $5,000 $4,236 $4,236 $764
Right of Way
$7,000 $0 $7,000 $2,382 $2,382 $4,618
Construction
$50,000 $-6,418 $43,582 $36,935 $36,935 $6,647
 
Total* $63,000 $-6,418 $56,582 $44,553 $44,553 $12,029

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/01/2000 

11/01/2006 
 

 
04/01/2000 

11/01/2006 
100  04/01/2000 

11/01/2006 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2009 

03/01/2011 
 

 
04/01/2009 

03/01/2011 
100  07/08/2009 

10/25/2010 
-3 

Begin Right of Way Phase

End Right of Way Phase
04/01/2009 

07/01/2010 
 

08/10/2011 
04/01/2009 

11/01/2010 
100  10/08/2009 

11/29/2010 
-6 

-1 
Begin Construction Phase

End Construction Phase
05/01/2011 

05/01/2013 
08/10/2011 

08/10/2011 
07/01/2011 

08/01/2013 
100  07/26/2011 

02/16/2015 
-1 

-19 
Begin Closeout Phase

End Closeout Phase
05/01/2013 

12/31/2013 
08/10/2011 

 
09/01/2013 

12/31/2013 
100  03/13/2015 

10/18/2021 
-19 

-95 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (Mixed) 4 1.0

Bond Funding Cost
Adopted:
$30,000,000
Current Approved:
$23,582,000
Actual Expenditures:
$22,160,052

 

Status as of December 31, 2023.