Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Sperry Road Extension Project |
Description: Extend Sperry Road
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Joaquin |
City | Stockton |
Zip Code | 95202 |
Senate District |
05 |
Assembly District | 17 |
Congressional District | 18 |
Caltrans District |
10 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 4 | 1.0 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Stockton | Wes Johnson | (209) 937-8088 | wes.johnson@stocktongov.com | |
Design (PS&E) Phase |
City of Stockton | Wes Johnson | (209) 937-8088 | wes.johnson@stocktongov.com | |
Right of Way Phase |
City of Stockton | Wes Johnson | (209) 937-8088 | wes.johnson@stocktongov.com | |
Construction Phase |
City of Stockton | James Wong | (209) 937-8110 | james.wong@stocktongov.com | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$30,000 | $-6,418 | $23,582 | ||||
Non-bond Funding | |||||||
Local** |
$33,000 | $0 | $33,000 | ||||
Total**** | $63,000 | $-6,418 | $56,582 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$1,000 | $0 | $1,000 | $1,000 | $1,000 | $0 | |
Design(PS&E) |
$5,000 | $0 | $5,000 | $4,236 | $4,236 | $764 | |
Right of Way |
$7,000 | $0 | $7,000 | $2,382 | $2,382 | $4,618 | |
Construction |
$50,000 | $-6,418 | $43,582 | $36,935 | $36,935 | $6,647 | |
Total* | $63,000 | $-6,418 | $56,582 | $44,553 | $44,553 | $12,029 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
04/01/2000 11/01/2006 |
|
04/01/2000 11/01/2006 |
100 | 04/01/2000 11/01/2006 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/01/2009 03/01/2011 |
|
04/01/2009 03/01/2011 |
100 | 07/08/2009 10/25/2010 |
-3 4 |
Begin Right of Way Phase
End Right of Way Phase |
04/01/2009 07/01/2010 |
08/10/2011 |
04/01/2009 11/01/2010 |
100 | 10/08/2009 11/29/2010 |
-6 -1 |
Begin Construction Phase
End Construction Phase |
05/01/2011 05/01/2013 |
08/10/2011 08/10/2011 |
07/01/2011 08/01/2013 |
100 | 07/26/2011 02/16/2015 |
-1 -19 |
Begin Closeout Phase
End Closeout Phase |
05/01/2013 12/31/2013 |
08/10/2011 |
09/01/2013 12/31/2013 |
100 | 03/13/2015 10/18/2021 |
-19 -95 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 4 | 1.0 |
Bond Funding Cost | |
---|---|
Adopted: |
$30,000,000 |
Current Approved: |
$23,582,000 |
Actual Expenditures: |
$22,160,052 |
Status as of December 31, 2023.