Marina Bay Parkway Grade Separation

Description: Construct Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Contra Costa
City Richmond
Zip Code 94804
 
Senate District
09
Assembly District 14
Congressional District 07
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Richmond Redevelopment Agency Michael Williams 510-307-8147   michael_williams@ci.richmond.ca.us
Design (PS&E) Phase
Richmond Redevelopment Agency Michael Williams 510-307-8147   michael_williams@ci.richmond.ca.us
Right of Way Phase
Richmond Redevelopment Agency Michael Williams 510-307-8147   michael_williams@ci.richmond.ca.us
Construction Phase
Richmond Redevelopment Agency Michael Williams 510-307-8147   michael_williams@ci.richmond.ca.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$18,975 $0 $18,975
LSR
$3,795 $-3,795 $0
Non-bond Funding
State/Federal*
$1,025 $5,930 $6,955
Local**
$14,155 $2,095 $16,250
 
Total**** $37,950 $4,230 $42,180

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$3,015 $-2,515 $500 $500 $500 $0
Design(PS&E)
$4,043 $-1,263 $2,780 $2,780 $2,780 $0
Right of Way
$1,573 $-1,473 $100 $100 $100 $0
Construction
$29,319 $9,481 $38,800 $37,369 $37,369 $1,431
 
Total* $37,950 $4,230 $42,180 $40,749 $40,749 $1,431

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/01/2008 

06/01/2009 
 

 
09/01/2008 

06/01/2009 
100  09/01/2008 

12/20/2010 


-19 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2008 

10/11/2010 
 

03/23/2011 
12/01/2008 

02/01/2011 
100  09/02/2009 

04/30/2011 
-9 

-3 
Begin Right of Way Phase

End Right of Way Phase
10/13/2009 

10/11/2010 
 

03/23/2011 
10/13/2009 

02/01/2011 
100  10/13/2009 

04/30/2011 


-3 
Begin Construction Phase

End Construction Phase
12/21/2010 

10/01/2013 
10/24/2012 

10/24/2012 
02/01/2013 

05/01/2015 
100  06/18/2013 

06/30/2017 
-5 

-26 
Begin Closeout Phase

End Closeout Phase
10/01/2013 

11/01/2013 
10/24/2012 

 
05/01/2015 

06/01/2015 
100  06/30/2017 

12/31/2017 
-26 

-31 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1 1

Bond Funding Cost
Adopted:
$22,770,000
Current Approved:
$18,413,000
Actual Expenditures:
$18,412,825

 

Status as of December 31, 2023.