Colton Crossing Grade Separation Project |
Description: Elevate Union Pacific east/west tracks over the BNSF's north/south tracks
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino |
City | Colton |
Zip Code | |
Senate District |
32 |
Assembly District | 62 |
Congressional District | 43 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 2 | |
Rail/Highway At-Grade Crossings Eliminated | 2 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
SANBAG | Garry Cohoe | (909) 884-8276 | gcohoe@sandag.ca.gov | |
Design (PS&E) Phase |
SANBAG | Garry Cohoe | (909) 884-8276 | gcohoe@sandag.ca.gov | |
Right of Way Phase |
SANBAG | Garry Cohoe | (909) 884-8276 | gcohoe@sandag.ca.gov | |
Construction Phase |
SANBAG | Garry Cohoe | (909) 884-8276 | gcohoe@sandag.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$91,305 | $-63,458 | $27,847 | ||||
Non-bond Funding | |||||||
State/Federal* |
$37,489 | $-33,800 | $3,689 | ||||
Private*** |
$73,200 | $-60,629 | $12,571 | ||||
Total**** | $201,994 | $-157,887 | $44,107 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$3,689 | $0 | $3,689 | $3,689 | $0 | $3,689 | |
Design(PS&E) |
$11,600 | $-6,030 | $5,570 | $5,570 | $0 | $5,570 | |
Right of Way |
$26,700 | $-26,267 | $433 | $433 | $0 | $433 | |
Construction |
$160,005 | $-86,220 | $73,785 | $73,784 | $0 | $73,785 | |
Total* | $201,994 | $-157,887 | $44,107 | $83,476 | $0 | $44,107 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/01/2007 11/30/2010 |
05/19/2010 |
01/01/2007 11/30/2010 |
100 | 05/06/2011 |
0 -5 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/30/2010 06/30/2011 |
05/19/2010 05/19/2010 |
06/30/2010 06/30/2011 |
100 | 06/21/2011 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
02/28/2011 06/30/2011 |
05/19/2010 05/19/2010 |
02/28/2011 06/30/2011 |
100 | 06/21/2011 |
0 0 |
Begin Construction Phase
End Construction Phase |
09/30/2011 03/30/2014 |
05/19/2010 05/19/2010 |
09/30/2011 03/30/2014 |
100 | 10/31/2011 03/31/2014 |
-1 0 |
Begin Closeout Phase
End Closeout Phase |
04/01/2014 05/01/2015 |
05/19/2010 |
04/01/2014 05/01/2015 |
100 | 04/01/2014 08/30/2014 |
0 8 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 2 | |
Rail/Highway At-Grade Crossings Eliminated | 2 |
Bond Funding Cost | |
---|---|
Adopted: |
$91,305,000 |
Current Approved: |
$27,847,000 |
Actual Expenditures: |
$27,846,147 |
Status as of December 31, 2023.