Colton Crossing Grade Separation Project

Description: Elevate Union Pacific east/west tracks over the BNSF's north/south tracks

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City Colton
Zip Code
 
Senate District
32
Assembly District 62
Congressional District 43
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated  2      
Rail/Highway At-Grade Crossings Eliminated      2  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
SANBAG Garry Cohoe (909) 884-8276   gcohoe@sandag.ca.gov
Design (PS&E) Phase
SANBAG Garry Cohoe (909) 884-8276   gcohoe@sandag.ca.gov
Right of Way Phase
SANBAG Garry Cohoe (909) 884-8276   gcohoe@sandag.ca.gov
Construction Phase
SANBAG Garry Cohoe (909) 884-8276   gcohoe@sandag.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$91,305 $-63,458 $27,847
Non-bond Funding
State/Federal*
$37,489 $-33,800 $3,689
Private***
$73,200 $-60,629 $12,571
 
Total**** $201,994 $-157,887 $44,107

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$3,689 $0 $3,689 $3,689 $0 $3,689
Design(PS&E)
$11,600 $-6,030 $5,570 $5,570 $0 $5,570
Right of Way
$26,700 $-26,267 $433 $433 $0 $433
Construction
$160,005 $-86,220 $73,785 $73,784 $0 $73,785
 
Total* $201,994 $-157,887 $44,107 $83,476 $0 $44,107

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2007 

11/30/2010 
 

05/19/2010 
01/01/2007 

11/30/2010 
100   

05/06/2011 


-5 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/30/2010 

06/30/2011 
05/19/2010 

05/19/2010 
06/30/2010 

06/30/2011 
100   

06/21/2011 


Begin Right of Way Phase

End Right of Way Phase
02/28/2011 

06/30/2011 
05/19/2010 

05/19/2010 
02/28/2011 

06/30/2011 
100   

06/21/2011 


Begin Construction Phase

End Construction Phase
09/30/2011 

03/30/2014 
05/19/2010 

05/19/2010 
09/30/2011 

03/30/2014 
100  10/31/2011 

03/31/2014 
-1 

Begin Closeout Phase

End Closeout Phase
04/01/2014 

05/01/2015 
05/19/2010 

 
04/01/2014 

05/01/2015 
100  04/01/2014 

08/30/2014 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 2
Rail/Highway At-Grade Crossings Eliminated 2

Bond Funding Cost
Adopted:
$91,305,000
Current Approved:
$27,847,000
Actual Expenditures:
$27,846,147

 

Status as of December 31, 2023.