Solano I-80/680/12 Connector

Description: Construct two-lane Westbound I-80 to Westbound SR 12 connector with bridge crossing over new Westbound I-80 Green Valley Road onramp. Reconstruct I-80/Green Valley interchange.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Solano
City Fairfield
Zip Code
 
Senate District
02, 05
Assembly District 08
Congressional District 10
 
Caltrans District
04
 
 
County/State Route Solano 12
Postmile Begin/End 2.5 2.8
 
County/State Route Solano 80
Postmile Begin/End 12 12.9
Project Benefits
 Benefit Baseline Actual
Ramp/Connectors Lane Miles  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Solano Transportation Authority Janet Adams 707-424-6010   jadams@sta-snci.com
Design (PS&E) Phase
Solano Transportation Authority Janet Adams 707-424-6010   jadams@sta-snci.com
Right of Way Phase
Solano Transportation Authority Janet Adams 707-424-6010   jadams@sta-snci.com
Construction Phase
Solano Transportation Authority Janet Adams 707-424-6010   jadams@sta-snci.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$24,000 $-1,153 $22,847
Non-bond Funding
State/Federal*
$11,412 $2,333 $13,745
Local**
$64,988 $0 $64,988
 
Total**** $100,400 $1,180 $101,580

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$3,500 $0 $3,500 $0 $0 $3,500
Design(PS&E)
$8,880 $0 $8,880 $0 $0 $8,880
Right of Way
$23,160 $0 $23,160 $0 $0 $23,160
Construction
$64,860 $1,180 $66,040 $0 $0 $66,040
 
Total* $100,400 $1,180 $101,580 $0 $0 $101,580

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/01/2003 

07/31/2012 
05/23/2012 

05/23/2012 
05/01/2003 

07/31/2012 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/30/2011 

03/15/2013 
05/23/2012 

06/11/2013 
12/30/2011 

05/31/2013 
100   

03/15/2013 


Begin Right of Way Phase

End Right of Way Phase
01/17/2012 

03/15/2013 
05/23/2012 

06/11/2013 
01/17/2012 

04/30/2013 
100   

08/04/2013 


-3 
Begin Construction Phase

End Construction Phase
08/31/2013 

12/31/2015 
06/11/2013 

06/11/2013 
09/30/2013 

01/31/2016 
100  03/19/2014 

03/01/2018 
-6 

-25 
Begin Closeout Phase

End Closeout Phase
01/01/2016 

01/01/2017 
06/11/2013 

 
01/31/2016 

01/31/2017 
25  03/01/2018 

12/31/2019 
-25 

-35 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Ramp/Connectors Lane Miles 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.