Solano I-80/680/12 Connector |
Description: Construct two-lane Westbound I-80 to Westbound SR 12 connector with bridge crossing over new Westbound I-80 Green Valley Road onramp. Reconstruct I-80/Green Valley interchange.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Solano |
City | Fairfield |
Zip Code | |
Senate District |
02, 05 |
Assembly District | 08 |
Congressional District | 10 |
Caltrans District |
04 |
County/State Route | Solano 12 |
Postmile Begin/End | 2.5 2.8 |
County/State Route | Solano 80 |
Postmile Begin/End | 12 12.9 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Ramp/Connectors Lane Miles | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Solano Transportation Authority | Janet Adams | 707-424-6010 | jadams@sta-snci.com | |
Design (PS&E) Phase |
Solano Transportation Authority | Janet Adams | 707-424-6010 | jadams@sta-snci.com | |
Right of Way Phase |
Solano Transportation Authority | Janet Adams | 707-424-6010 | jadams@sta-snci.com | |
Construction Phase |
Solano Transportation Authority | Janet Adams | 707-424-6010 | jadams@sta-snci.com | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$24,000 | $-1,153 | $22,847 | ||||
Non-bond Funding | |||||||
State/Federal* |
$11,412 | $2,333 | $13,745 | ||||
Local** |
$64,988 | $0 | $64,988 | ||||
Total**** | $100,400 | $1,180 | $101,580 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$3,500 | $0 | $3,500 | $0 | $0 | $3,500 | |
Design(PS&E) |
$8,880 | $0 | $8,880 | $0 | $0 | $8,880 | |
Right of Way |
$23,160 | $0 | $23,160 | $0 | $0 | $23,160 | |
Construction |
$64,860 | $1,180 | $66,040 | $0 | $0 | $66,040 | |
Total* | $100,400 | $1,180 | $101,580 | $0 | $0 | $101,580 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
05/01/2003 07/31/2012 |
05/23/2012 05/23/2012 |
05/01/2003 07/31/2012 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/30/2011 03/15/2013 |
05/23/2012 06/11/2013 |
12/30/2011 05/31/2013 |
100 | 03/15/2013 |
0 3 |
Begin Right of Way Phase
End Right of Way Phase |
01/17/2012 03/15/2013 |
05/23/2012 06/11/2013 |
01/17/2012 04/30/2013 |
100 | 08/04/2013 |
0 -3 |
Begin Construction Phase
End Construction Phase |
08/31/2013 12/31/2015 |
06/11/2013 06/11/2013 |
09/30/2013 01/31/2016 |
100 | 03/19/2014 03/01/2018 |
-6 -25 |
Begin Closeout Phase
End Closeout Phase |
01/01/2016 01/01/2017 |
06/11/2013 |
01/31/2016 01/31/2017 |
25 | 03/01/2018 12/31/2019 |
-25 -35 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Ramp/Connectors Lane Miles | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.