Sacramento Intermodal Track Relocation

Description: Relocate Union Pacific Mainline Track

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City Sacramento
Zip Code
 
Senate District
06
Assembly District 09
Congressional District 05
 
Caltrans District
03
 
 
County/State Route Sacramento 80
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Track Miles Realigned  .6      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Sacramento Saed Hasan 916-808-7923   shasan@cityofsacramento.org
Design (PS&E) Phase
City of Sacramento Saed Hasan 916-808-7923   shasan@cityofsacramento.org
Right of Way Phase
City of Sacramento Saed Hasan 916-808-7923   shasan@cityofsacramento.org
Construction Phase
City of Sacramento Saed Hasan 916-808-7923   shasan@cityofsacramento.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$25,266 $0 $25,266
SLPP
$0 $3,500 $3,500
Non-bond Funding
State/Federal*
$20,000 $-9,191 $10,809
Local**
$11,584 $9,086 $20,670
 
Total**** $56,850 $3,395 $60,245

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$2,000 $1,255 $3,255 $0 $0 $3,255
Design(PS&E)
$4,984 $1,881 $6,865 $0 $0 $6,865
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$49,866 $21,306 $71,172 $0 $0 $71,172
 
Total* $56,850 $3,395 $60,245 $0 $0 $60,245

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/23/2008 

04/30/2009 
 

02/22/2012 
01/23/2008 

08/31/2009 
100  01/23/2008 

08/31/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/01/2009 

08/31/2009 
 

02/22/2012 
05/01/2009 

01/31/2012 
100  05/01/2009 

01/18/2011 


13 
Begin Right of Way Phase

End Right of Way Phase
05/01/2009 

08/31/2009 
 

02/22/2012 
05/01/2009 

08/31/2011 
100  05/01/2009 

11/30/2009 


21 
Begin Construction Phase

End Construction Phase
01/02/2010 

12/31/2011 
02/22/2012 

02/22/2012 
03/31/2011 

01/31/2013 
100  03/22/2011 

09/16/2013 


-8 
Begin Closeout Phase

End Closeout Phase
01/01/2012 

06/30/2012 
02/22/2012 

 
01/31/2013 

10/31/2013 
100  08/15/2013 

05/31/2014 
-7 

-7 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Track Miles Realigned .6

Bond Funding Cost
Adopted:
$25,266,000
Current Approved:
$25,266,000
Actual Expenditures:
$25,266,000

 

Status as of December 31, 2023.