Caltrans Logo

West Sacramento Rail Plan

Description: Phase 5 (Pioneer Bluff Bridge) of a larger Rail project will increase rail capacity and provide vehicular alternative to avoid delays on US50

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Yolo
City West Sacramento
Zip Code 95691
 
Senate District
06
Assembly District 07
Congressional District 06
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Nbr Structures Modified  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of West Sacramento Vin Cay 916-617-4669   vinc@cityofwestsacramento.org
Design (PS&E) Phase
City of West Sacramento Vin Cay 916-617-4669   vinc@cityofwestsacramento.org
Right of Way Phase
City of West Sacramento Vin Cay 916-617-4669   vinc@cityofwestsacramento.org
Construction Phase
City of West Sacramento Vin Cay 916-617-4669   vinc@cityofwestsacramento.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$9,678 $0 $9,678
Non-bond Funding
State/Federal*
$960 $0 $960
Local**
$2,418 $-500 $1,918
Private***
$9,469 $500 $9,969
 
Total**** $22,525 $0 $22,525

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$213 $0 $213 $180 $180 $33
Design(PS&E)
$853 $0 $853 $680 $680 $173
Right of Way
$25 $0 $25 $5 $5 $20
Construction
$21,434 $0 $21,434 $11,350 $11,350 $10,084
 
Total* $22,525 $0 $22,525 $12,215 $12,215 $10,310

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/30/2008 

05/15/2013 
 

03/05/2013 
05/30/2008 

03/05/2013 
100  05/30/2008 

03/05/2013 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2007 

12/30/2013 
 

 
07/01/2007 

12/30/2013 
100  07/01/2007 

12/30/2013 


Begin Right of Way Phase

End Right of Way Phase
12/01/2012 

08/15/2013 
 

 
12/01/2012 

08/15/2013 
100  12/01/2012 

08/15/2013 


Begin Construction Phase

End Construction Phase
07/11/2011 

12/31/2014 
 

 
07/11/2011 

12/31/2014 
100  07/11/2011 

12/22/2015 


-12 
Begin Closeout Phase

End Closeout Phase
01/25/2012 

06/30/2015 
 

 
01/25/2012 

06/30/2015 
03/01/2019 

03/31/2021 
-86 

-70 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Nbr Structures Modified 1

Bond Funding Cost
Adopted:
$9,678,000
Current Approved:
$9,678,000
Actual Expenditures:
$9,678,000

 

Status as of December 31, 2023.