Sorrento Valley Double Track Project

Description: Construct 1.1 miles of new double track, raise track elevation, replace 2 timber trestles, and construct improvements for double track realignment

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego
City San Diego
Zip Code
 
Senate District
39
Assembly District 76
Congressional District 50
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Additional Track Miles Layed  1.1    1.1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
SANDAG Bruce Smith 619-699-1907   bsm@sandag.org
Design (PS&E) Phase
SANDAG Bruce Smith 619-699-1907   bsm@sandag.org
Right of Way Phase
SANDAG Bruce Smith 619-699-1907   bsm@sandag.org
Construction Phase
SANDAG Bruce Smith 619-699-1907   bsm@sandag.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$14,313 $-1,319 $12,994
Non-bond Funding
Local**
$23,387 $-1,571 $21,816
 
Total**** $37,700 $-2,890 $34,810

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$3,352 $0 $3,352 $3,393 $3,393 $-41
Design(PS&E)
$1,653 $0 $1,653 $1,513 $1,513 $140
Right of Way
$345 $0 $345 $396 $396 $-51
Construction
$32,350 $-2,890 $29,460 $27,332 $27,332 $2,128
 
Total* $37,700 $-2,890 $34,810 $32,634 $32,634 $2,176

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2009 

07/01/2012 
 

 
07/01/2009 

07/01/2012 
100  07/01/2009 

07/01/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2010 

04/30/2013 
 

 
07/01/2010 

04/30/2013 
100  07/01/2010 

04/30/2013 


Begin Right of Way Phase

End Right of Way Phase
01/01/2012 

04/01/2013 
 

 
01/01/2012 

04/01/2013 
100  01/01/2012 

04/01/2013 


Begin Construction Phase

End Construction Phase
11/01/2013 

11/01/2015 
 

 
11/01/2013 

11/01/2015 
100  10/25/2013 

03/31/2016 


-5 
Begin Closeout Phase

End Closeout Phase
11/01/2015 

11/01/2020 
 

 
11/01/2015 

11/01/2020 
100  11/01/2015 

11/01/2020 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Additional Track Miles Layed 1.1 1.1

Bond Funding Cost
Adopted:
$14,313,000
Current Approved:
$12,994,000
Actual Expenditures:
$12,055,199

 

Status as of December 31, 2023.