Puente Avenue Grade Separation Project

Description: Construct a roadway underpass for Puente Avenue, a bridge for Valley Blvd, and double-track bridge for UP trains.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Industry
Zip Code
 
Senate District
22
Assembly District 49
Congressional District 32
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
ACE Construction Authority Mark Christoffels 626-373-2691   mchristoffels@sgvcog.org
Design (PS&E) Phase
ACE Construction Authority Mark Christoffels 626-373-2691   mchristoffels@sgvcog.org
Right of Way Phase
ACE Construction Authority Mark Christoffels 626-373-2691   mchristoffels@sgvcog.org
Construction Phase
ACE Construction Authority Mark Christoffels 626-373-2691   mchristoffels@sgvcog.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$48,000 $0 $48,000
Non-bond Funding
Local**
$51,019 $0 $51,019
 
Total**** $99,019 $0 $99,019

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$300 $0 $300 $300 $0 $300
Design(PS&E)
$9,090 $0 $9,090 $9,111 $0 $9,090
Right of Way
$32,868 $0 $32,868 $35,385 $0 $32,868
Construction
$56,761 $0 $56,761 $52,808 $0 $56,761
 
Total* $99,019 $0 $99,019 $97,604 $0 $99,019

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/31/2012 

05/31/2012 
01/29/2014 

01/29/2014 
03/31/2012 

05/31/2012 
100  03/31/2012 

05/31/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/31/2012 

06/30/2013 
01/29/2014 

01/29/2014 
05/31/2012 

06/30/2013 
100  05/31/2012 

06/30/2013 


Begin Right of Way Phase

End Right of Way Phase
06/30/2013 

01/31/2014 
01/29/2014 

01/29/2014 
06/30/2013 

01/31/2014 
100  06/30/2012 

01/31/2014 
12 

Begin Construction Phase

End Construction Phase
09/30/2014 

09/30/2017 
01/29/2014 

01/29/2014 
09/30/2014 

09/30/2017 
100  12/15/2014 

07/13/2018 
-3 

-10 
Begin Closeout Phase

End Closeout Phase
10/31/2014 

03/31/2018 
01/29/2014 

 
10/31/2017 

03/31/2018 
100  01/15/2019 

12/31/2019 
-15 

-21 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1 1

Bond Funding Cost
Adopted:
$48,000,000
Current Approved:
$44,309,000
Actual Expenditures:
$44,308,735

 

Status as of December 31, 2023.