Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Puente Avenue Grade Separation Project |
Description: Construct a roadway underpass for Puente Avenue, a bridge for Valley Blvd, and double-track bridge for UP trains.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Industry |
Zip Code | |
Senate District |
22 |
Assembly District | 49 |
Congressional District | 32 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
ACE Construction Authority | Mark Christoffels | 626-373-2691 | mchristoffels@sgvcog.org | |
Design (PS&E) Phase |
ACE Construction Authority | Mark Christoffels | 626-373-2691 | mchristoffels@sgvcog.org | |
Right of Way Phase |
ACE Construction Authority | Mark Christoffels | 626-373-2691 | mchristoffels@sgvcog.org | |
Construction Phase |
ACE Construction Authority | Mark Christoffels | 626-373-2691 | mchristoffels@sgvcog.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$48,000 | $0 | $48,000 | ||||
Non-bond Funding | |||||||
Local** |
$51,019 | $0 | $51,019 | ||||
Total**** | $99,019 | $0 | $99,019 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$300 | $0 | $300 | $300 | $0 | $300 | |
Design(PS&E) |
$9,090 | $0 | $9,090 | $9,111 | $0 | $9,090 | |
Right of Way |
$32,868 | $0 | $32,868 | $35,385 | $0 | $32,868 | |
Construction |
$56,761 | $0 | $56,761 | $52,808 | $0 | $56,761 | |
Total* | $99,019 | $0 | $99,019 | $97,604 | $0 | $99,019 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
03/31/2012 05/31/2012 |
01/29/2014 01/29/2014 |
03/31/2012 05/31/2012 |
100 | 03/31/2012 05/31/2012 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/31/2012 06/30/2013 |
01/29/2014 01/29/2014 |
05/31/2012 06/30/2013 |
100 | 05/31/2012 06/30/2013 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
06/30/2013 01/31/2014 |
01/29/2014 01/29/2014 |
06/30/2013 01/31/2014 |
100 | 06/30/2012 01/31/2014 |
12 0 |
Begin Construction Phase
End Construction Phase |
09/30/2014 09/30/2017 |
01/29/2014 01/29/2014 |
09/30/2014 09/30/2017 |
100 | 12/15/2014 07/13/2018 |
-3 -10 |
Begin Closeout Phase
End Closeout Phase |
10/31/2014 03/31/2018 |
01/29/2014 |
10/31/2017 03/31/2018 |
100 | 01/15/2019 12/31/2019 |
-15 -21 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$48,000,000 |
Current Approved: |
$44,309,000 |
Actual Expenditures: |
$44,308,735 |
Status as of December 31, 2023.