Fairway Drive Grade Separation |
Description: construct an underpass on Fairway Drive, north of SR 60, and double track railroad bridge for UP trains.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Los Angeles |
City | Industry |
Zip Code | 91789 |
Senate District |
22 |
Assembly District | 49 |
Congressional District | 32 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
ACE Construction Authority | Martin Moreno | (626) 696-9104 | mmoreno@sgvcog.org | |
Design (PS&E) Phase |
ACE Construction Authority | Martin Moreno | (626) 696-9104 | mmoreno@sgvcog.org | |
Right of Way Phase |
ACE Construction Authority | Martin Moreno | (626) 696-9104 | mmoreno@sgvcog.org | |
Construction Phase |
ACE Construction Authority | Martin Moreno | (626) 696-9104 | mmoreno@sgvcog.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$71,000 | $0 | $71,000 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$71,213 | $0 | $71,213 | ||||
Total**** | $142,213 | $0 | $142,213 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$300 | $0 | $300 | $0 | $0 | $300 | |
Design(PS&E) |
$8,456 | $0 | $8,456 | $8,189 | $8,189 | $267 | |
Right of Way |
$38,655 | $0 | $38,655 | $35,760 | $35,713 | $2,942 | |
Construction |
$94,802 | $0 | $94,802 | $153,009 | $218,709 | $-123,907 | |
Total* | $142,213 | $0 | $142,213 | $196,958 | $262,611 | $-120,398 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
11/30/2011 10/31/2012 |
01/29/2014 01/29/2014 |
11/30/2011 10/31/2012 |
100 | 11/30/2011 10/31/2012 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
11/30/2011 09/30/2013 |
01/29/2014 01/29/2014 |
11/30/2011 09/30/2013 |
100 | 11/30/2011 04/28/2014 |
0 -7 |
Begin Right of Way Phase
End Right of Way Phase |
10/31/2012 04/30/2014 |
01/29/2014 01/29/2014 |
10/31/2012 04/30/2014 |
100 | 10/01/2012 04/30/2014 |
1 0 |
Begin Construction Phase
End Construction Phase |
12/31/2014 06/30/2018 |
01/29/2014 01/29/2014 |
12/31/2014 06/30/2018 |
99 | 10/28/2014 04/01/2024 |
2 -70 |
Begin Closeout Phase
End Closeout Phase |
07/31/2018 12/31/2018 |
01/29/2014 |
07/31/2018 12/31/2018 |
0 | 05/01/2024 11/01/2024 |
-70 -71 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.