Natoma Overhead Widening and On Ramp Improvements

Description: Widen the Natoma Overhead by two lanes to accommodate eastbound loop on ramp weave and new transition lane for congestion relief.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Sacramento
City Folsom
Zip Code
 
Senate District

Assembly District
Congressional District
 
Caltrans District
03
 
 
County/State Route Sacramento 50
Postmile Begin/End 16.9 17.4
Project Benefits
 Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified)  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans John Holder (530) 741-5448   john.holder@dot.ca.gov
Design (PS&E) Phase
Caltrans John Holder (530) 741-5448   john.holder@dot.ca.gov
Right of Way Phase
Caltrans John Holder (530) 741-5448   john.holder@dot.ca.gov
Construction Phase
Caltrans John Holder (530) 741-5448   john.holder@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$8,000 $-41 $7,959
Non-bond Funding
Local**
$500 $0 $500
 
Total**** $8,500 $-41 $8,459

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$125 $0 $125 $0 $0 $125
Design(PS&E)
$198 $0 $198 $0 $0 $198
Right of Way
$253 $0 $253 $0 $0 $253
Construction
$7,924 $-41 $7,883 $0 $0 $7,883
 
Total* $8,500 $-41 $8,459 $0 $0 $8,459

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

12/30/2008 
 

05/21/2014 
 

12/30/2008 
100   

12/30/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2013 

05/15/2014 
05/21/2014 

05/21/2014 
10/01/2013 

05/15/2014 
100  10/01/2013 

05/15/2014 


Begin Right of Way Phase

End Right of Way Phase
10/01/2013 

05/01/2014 
05/21/2014 

05/21/2014 
10/01/2013 

05/01/2014 
100  10/01/2013 

05/01/2014 


Begin Construction Phase

End Construction Phase
12/01/2014 

12/01/2015 
05/21/2014 

05/21/2014 
12/01/2014 

12/01/2015 
100  12/01/2014 

04/21/2016 


-5 
Begin Closeout Phase

End Closeout Phase
12/01/2015 

12/01/2017 
05/21/2014 

 
12/01/2015 

12/01/2017 
04/21/2016 

12/01/2017 
-5 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified) 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.