Natoma Overhead Widening and On Ramp Improvements |
Description: Widen the Natoma Overhead by two lanes to accommodate eastbound loop on ramp weave and new transition lane for congestion relief.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Sacramento |
City | Folsom |
Zip Code | |
Senate District |
|
Assembly District | |
Congressional District | |
Caltrans District |
03 |
County/State Route | Sacramento 50 |
Postmile Begin/End | 16.9 17.4 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified or Improved Interchanges (Nbr Modified) | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | John Holder | (530) 741-5448 | john.holder@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | John Holder | (530) 741-5448 | john.holder@dot.ca.gov | |
Right of Way Phase |
Caltrans | John Holder | (530) 741-5448 | john.holder@dot.ca.gov | |
Construction Phase |
Caltrans | John Holder | (530) 741-5448 | john.holder@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$8,000 | $-41 | $7,959 | ||||
Non-bond Funding | |||||||
Local** |
$500 | $0 | $500 | ||||
Total**** | $8,500 | $-41 | $8,459 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$125 | $0 | $125 | $0 | $0 | $125 | |
Design(PS&E) |
$198 | $0 | $198 | $0 | $0 | $198 | |
Right of Way |
$253 | $0 | $253 | $0 | $0 | $253 | |
Construction |
$7,924 | $-41 | $7,883 | $0 | $0 | $7,883 | |
Total* | $8,500 | $-41 | $8,459 | $0 | $0 | $8,459 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
12/30/2008 |
05/21/2014 |
12/30/2008 |
100 | 12/30/2008 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/01/2013 05/15/2014 |
05/21/2014 05/21/2014 |
10/01/2013 05/15/2014 |
100 | 10/01/2013 05/15/2014 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
10/01/2013 05/01/2014 |
05/21/2014 05/21/2014 |
10/01/2013 05/01/2014 |
100 | 10/01/2013 05/01/2014 |
0 0 |
Begin Construction Phase
End Construction Phase |
12/01/2014 12/01/2015 |
05/21/2014 05/21/2014 |
12/01/2014 12/01/2015 |
100 | 12/01/2014 04/21/2016 |
0 -5 |
Begin Closeout Phase
End Closeout Phase |
12/01/2015 12/01/2017 |
05/21/2014 |
12/01/2015 12/01/2017 |
0 | 04/21/2016 12/01/2017 |
-5 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified or Improved Interchanges (Nbr Modified) | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.