Raymond Avenue Grade Separation

Description: Construct a Grade Separation on Raymond Ave at BNSF railroad crossing between Walnut Avenue and Ash Avenue.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Fullerton
Zip Code 92832
 
Senate District
29
Assembly District 79
Congressional District 42
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Rail/Highway At-Grade Crossings Eliminated  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Fullerton Yelena Voronel 714-738-6852   yelenav@ci.fullerton.ca.us
Design (PS&E) Phase
City of Fullerton Yelena Voronel 714-738-6852   yelenav@ci.fullerton.ca.us
Right of Way Phase
OCTA Andy Muth 714-560-5408   amuth@octa.net
Construction Phase
City of Fullerton Yelena Voronel 714-738-6852   yelenav@ci.fullerton.ca.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$11,890 $-1,490 $10,400
Non-bond Funding
State/Federal*
$78,667 $0 $78,667
Local**
$21,633 $0 $21,633
 
Total**** $112,190 $-1,490 $110,700

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $1,177 $1,177 $-1,177
Design(PS&E)
$5,370 $0 $5,370 $4,231 $4,231 $1,139
Right of Way
$34,901 $0 $34,901 $32,181 $32,181 $2,720
Construction
$71,919 $-1,490 $70,429 $87,892 $87,892 $-17,463
 
Total* $112,190 $-1,490 $110,700 $125,480 $125,480 $-14,780

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/10/2009 

11/16/2009 
01/29/2014 

01/29/2014 
02/10/2009 

11/16/2009 
100  02/10/2009 

11/16/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/30/2010 

12/14/2012 
01/29/2014 

01/29/2014 
03/30/2010 

12/14/2012 
100  03/30/2010 

12/14/2012 


Begin Right of Way Phase

End Right of Way Phase
12/11/2011 

07/31/2013 
01/29/2014 

01/29/2014 
12/11/2011 

07/31/2013 
100  12/11/2011 

07/31/2013 


Begin Construction Phase

End Construction Phase
07/29/2014 

07/15/2018 
01/29/2014 

01/29/2014 
07/29/2014 

07/15/2018 
100  02/04/2014 

05/14/2018 


Begin Closeout Phase

End Closeout Phase
07/15/2018 

07/15/2021 
01/29/2014 

 
07/15/2018 

07/15/2021 
100  07/15/2018 

07/15/2021 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail/Highway At-Grade Crossings Eliminated 1 1

Bond Funding Cost
Adopted:
$11,890,000
Current Approved:
$11,890,000
Actual Expenditures:
$10,400,000

 

Status as of December 31, 2023.