US 50 HOV Lanes - Corridor Project

Description: In El Dorado County. Add HOV lanes on Rte 50 from El Dorado Hills Blvd to west of Bass Lake Rd Interchange.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
El Dorado
City Cameron Park, El Dorado Hills
Zip Code 95682, 95762
 
Senate District
01
Assembly District 10
Congressional District 04
 
Caltrans District
03
 
 
County/State Route El Dorado 50
Postmile Begin/End 0
 
County/State Route El Dorado 50
Postmile Begin/End 0.2 2.9
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  2295    691  
Lane Miles Added (HOV)  7.0    7.3  
Peak Period Time Savings (minutes)  167560    47,460  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
El Dorado County DOT Adam Bane 530-621-5983   adam.bane@edcgov.us
Design (PS&E) Phase
El Dorado County DOT Adam Bane 530-621-5983   adam.bane@edcgov.us
Right of Way Phase
El Dorado County DOT Adam Bane 530-621-5983   adam.bane@edcgov.us
Construction Phase
El Dorado County DOT Adam Bane 530-621-5983   adam.bane@edcgov.us
 
Corridor System Management Plan
Caltrans Jeff Pulverman (916) 274-0638   jeff.pulverman@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$29,500 $-3,340 $26,160
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$26,520 $2,208 $28,728
Non Budgeted ETC
$0 $0 $0
 
Total**** $56,020 $-1,132 $54,888

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$0 $0 $0 $985
Design(PS&E)
$4,600 $0 $4,600 $6,911
Right of Way
$260 $0 $260 $14
Construction
$51,160 $-1,132 $50,028 $52,022
 
Total* $56,020 $-1,132 $54,888 $59,931

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/30/1999 

06/01/2002 
 

 
12/30/1999 

06/01/2002 
100  04/01/1999 

06/28/2002 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2007 

05/01/2008 
 

 
03/01/2007 

05/01/2008 
100  03/01/2007 

08/26/2008 


-4 
Begin Right of Way Phase

End Right of Way Phase
06/01/2007 

05/01/2008 
 

 
06/01/2007 

05/01/2008 
100  04/01/2007 

04/22/2008 


Begin Construction Phase

End Construction Phase
12/01/2008 

06/01/2010 
 

 
12/01/2008 

06/01/2010 
100  11/18/2008 

11/07/2012 


-30 
Begin Closeout Phase

End Closeout Phase
08/01/2010 

08/01/2011 
 

 
08/01/2010 

08/01/2011 
100  11/07/2012 

07/01/2017 
-28 

-72 
Corridor System Management Plan
Adoption Date 03/01/2009    03/01/2009  100  05/01/2009  -2 
Implementation Date 07/01/2010    07/01/2010  06/01/2009  13 
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 2295 691
Lane Miles Added (HOV) 7.0 7.3
Peak Period Time Savings (minutes) 167560 47,460

Bond Funding Cost
Adopted:
$29,500,000
Current Approved:
$26,294,000
Actual Expenditures:
$25,471,000

 

Status as of December 31, 2023.