Caltrans Logo

Oakley to Port Chicago Double Track (Segment 3)

Description: Between Oakley and Port Chicago, through the communities of Antioch and Pittsburgh. Construct second main track, crossovers, and related track and signal work.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Contra Costa
City Antioch, Pittsburg
Zip Code
 
Senate District
05, 07, 12, 14, 16, 18
Assembly District 15, 25, 26, 29, 30, 31, 32, 34
Congressional District 10, 11, 18, 19, 20, 21, 22
 
Caltrans District

 
 
County/State Route Contra Costa SJ
Postmile Begin/End 1146 1164
CC = Capital Corridor
PS = Pacific Surfliner
SJ = San Joaquin
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Gary Atwal 916-657-1798   Gary.Atwal@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RAIL
$25,450 $-2,300 $23,150
Non-bond Funding
 
Total**** $25,450 $-2,300 $23,150

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$25,450 $-2,300 $23,150 $23,148 $23,148 $2
 
Total* $25,450 $-2,300 $23,150 $23,148 $23,148 $2

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2008 

05/31/2012 
06/22/2011 

06/22/2011 
07/01/2008 

05/31/2012 
09/01/2012 

08/31/2015 
-51 

-40 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2012 

03/01/2015 
06/22/2011 

05/28/2015 
09/01/2012 

02/28/2017 
82  09/01/2012 

02/28/2017 


Begin Closeout Phase

End Closeout Phase
04/01/2015 

10/31/2015 
05/28/2015 

05/28/2015 
03/01/2017 

08/31/2017 
03/01/2017 

08/31/2017 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours)

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.