Title | County | State Route |
Total Project Cost (x1000) |
Total Bond Funding* (x1000) |
Planned Construction Start |
Planned Construction Finish |
Cool Port Oakland
|
Alameda | N/A | $91,905 | $5,000 | Aug 01, 2016 | Oct 01, 2017 |
I-580 Truck Climbing Lane
|
Alameda | 580 | $44,903 | $44,903 | Jun 01, 2012 | Apr 01, 2015 |
I-880 Reconstruction (29th and 23rd Avenues)
|
Alameda | 880 | $97,912 | $73,000 | Jul 31, 2013 | Jul 31, 2017 |
Outer Harbor Intermodal Terminal
|
Alameda | $499,241 | $242,141 | Jan 01, 2010 | Dec 31, 2019 | |
Marina Bay Parkway Grade Separation
|
Contra Costa | $42,180 | $18,975 | Feb 01, 2013 | May 01, 2015 | |
Richmond Rail Connector
|
Contra Costa | $21,324 | $9,555 | Dec 31, 2013 | Oct 31, 2015 | |
Brawley Bypass (State Route 78 and 111 Expressway) Stage 3
|
Imperial | 78 | $69,334 | $42,572 | Nov 30, 2010 | Mar 31, 2014 |
Tehachapi Trade Corridor Project
|
Kern | 58 | $26,040 | $12,270 | Sep 24, 2014 | Oct 01, 2016 |
Alameda Corridor West Terminus Intermodal Railyard-West Basin Railyard Extension
|
Los Angeles | $72,987 | $20,712 | Nov 21, 2013 | Feb 28, 2016 | |
Baldwin Avenue Grade Separation
|
Los Angeles | $71,571 | $27,739 | Aug 31, 2012 | Aug 31, 2014 | |
C Street Access Ramps Improvement
|
Los Angeles | 110 | $38,427 | $7,836 | Nov 01, 2013 | Oct 31, 2016 |
Cargo Transportation Improvement Emission Reduction Program
|
Los Angeles | $147,250 | $35,665 | Jan 31, 2013 | Sep 30, 2017 | |
Citrus Avenue Crossing Improvements
|
Los Angeles | $3,485 | $1,455 | Oct 30, 2016 | Apr 30, 2018 | |
Control Point Soledad Speed Increase
|
Los Angeles | $6,648 | $2,708 | Oct 01, 2016 | Apr 30, 2018 | |
Durfee Avenue Grade Separation Project
|
Los Angeles | $91,143 | $2,620 | Oct 31, 2018 | Jul 31, 2021 | |
Everport Terminal Berth Efficiency and Emission Reduction Project
|
Los Angeles | $21,967 | $5,430 | May 19, 2019 | Jun 07, 2021 | |
Fairway Drive Grade Separation
|
Los Angeles | $142,213 | $71,000 | Dec 31, 2014 | Jun 30, 2018 | |
Fullerton Road Grade Separation
|
Los Angeles | $113,604 | $35,060 | Mar 30, 2016 | Dec 30, 2019 | |
Gateway (Valley View Grade Separation)
|
Los Angeles | $63,997 | $18,012 | May 31, 2012 | Aug 31, 2014 | |
Gerald Desmond Bridge Replacement
|
Los Angeles | 710 | $1,336,061 | $299,795 | Jun 07, 2013 | Jun 27, 2016 |
I-110 Freeway Access Ramp State Route 47 and 110 Northbound Connector Widening
|
Los Angeles | 47, 110, 110 | $40,773 | $13,205 | Jun 30, 2013 | Jun 30, 2015 |
Middle Harbor Terminal Redeveloment
|
Los Angeles | N/A | $156,355 | $15,436 | Dec 01, 2017 | Sep 30, 2020 |
New Freight Siding Antelope Valley Line
|
Los Angeles | $11,163 | $4,771 | Aug 27, 2010 | Mar 30, 2011 | |
Ports Rail System Tier 1 (West Basin Rail Access Improvements
|
Los Angeles | $135,097 | $50,141 | Jun 01, 2012 | Jul 01, 2014 | |
Ports Rail System Tier I (Pier F Support Yard)
|
Los Angeles | $29,142 | $4,093 | Nov 29, 2012 | May 15, 2014 | |
Ports Rail System Tier I (Track Realignment at Ocean Boulevard)
|
Los Angeles | $55,540 | $16,216 | Nov 29, 2012 | May 15, 2014 | |
Puente Avenue Grade Separation Project
|
Los Angeles | $99,019 | $48,000 | Sep 30, 2014 | Sep 30, 2017 | |
Ramona Boulevard Crossing Improvements
|
Los Angeles | $3,485 | $1,455 | Oct 30, 2016 | Apr 30, 2018 | |
San Gabriel Valley Grade Separation Program
|
Los Angeles | $595,510 | $237,778 | Jun 30, 2004 | Sep 30, 2017 | |
South Wilmington Grade Separation
|
Los Angeles | $73,582 | $13,759 | Nov 01, 2012 | Nov 01, 2014 | |
TraPac Terminal Automation - Automated Shuttle Carrier Maintenance & Repair (M&R) Facility
|
Los Angeles | $5,681 | $2,840 | Jul 31, 2015 | Aug 31, 2016 | |
Vincent Siding at CP Quartz and 2nd Platform at Vincent/Acton Grade Station
|
Los Angeles | $17,400 | $8,200 | Apr 30, 2015 | Dec 31, 2016 | |
Washington Boulevard Widening and Reconstruction Project
|
Los Angeles | $32,000 | $5,800 | Dec 15, 2014 | Mar 01, 2016 | |
YTI Terminal Enhancement & Truck Trip Reduction Program
|
Los Angeles | $51,198 | $9,533 | Jul 14, 2015 | May 12, 2017 | |
Sanborn Rd/US101 Interchange Improvements and Elvee Drive Extension
|
Monterey | $4,300 | $1,700 | May 26, 2015 | May 26, 2016 | |
I-405 HOV Lane
|
Orange | 405 | $1,506,136 | $7,771 | Jan 31, 2017 | Aug 31, 2026 |
I-5 Improvement from SR-73 to Oso Parkway (Segment 1)
|
Orange | 5 | $179,768 | $26,991 | Oct 01, 2019 | Jan 01, 2024 |
Kraemer Blvd Undercrossing
|
Orange | $53,185 | $15,513 | Oct 01, 2011 | May 01, 2014 | |
Lakeview Avenue Overcrossing
|
Orange | $91,149 | $27,520 | Sep 01, 2013 | Dec 01, 2015 | |
Orangethorpe Avenue Grade Separation
|
Orange | $95,325 | $30,324 | Mar 01, 2013 | Jul 01, 2016 | |
Placentia Avenue Undercrossing
|
Orange | $56,794 | $9,548 | Oct 01, 2011 | May 01, 2014 | |
Raymond Avenue Grade Separation
|
Orange | $110,700 | $10,400 | Jul 29, 2014 | Jul 15, 2018 | |
State College Grade Separation
|
Orange | $71,554 | $32,800 | Nov 01, 2013 | Aug 01, 2016 | |
State Route 91 (Auxiliary Lanes on Westbound State Route 91 between State Route 57 and I-5)
|
Orange | 91 | $44,268 | $25,438 | Dec 01, 2012 | Dec 01, 2015 |
Tustin Avenue and Rose Drive Overcrossing
|
Orange | $86,381 | $30,862 | Mar 01, 2013 | Sep 01, 2015 | |
I-80/SR-65 Interchange Phase I-Third Lane Project
|
Placer | 65 | $43,053 | $3,600 | Nov 14, 2017 | Nov 01, 2020 |
ACE: Avenue 66/UP Railroad Grade Separation Bypass
|
Riverside | N/A | $39,080 | $5,709 | Jul 30, 2019 | Jul 29, 2021 |
Auto Center Drive Grade Separation
|
Riverside | $32,675 | $16,000 | Nov 01, 2011 | Apr 30, 2013 | |
Avenue 52 Grade Separation Project
|
Riverside | $33,516 | $9,766 | Oct 15, 2013 | Mar 31, 2015 | |
Avenue 56 Grade Separation Union Pacific Yuma Subdivision
|
Riverside | $29,394 | $12,802 | Dec 01, 2013 | Feb 28, 2016 | |
Clay Street Grade Separation
|
Riverside | $30,806 | $13,247 | Dec 01, 2013 | Jun 15, 2016 | |
Columbia Avenue Grade Separation
|
Riverside | $33,003 | $4,953 | Sep 01, 2008 | Dec 01, 2009 | |
Iowa Avenue Grade Separation
|
Riverside | $32,000 | $13,000 | Jun 26, 2012 | Nov 01, 2013 | |
Magnolia Avenue Grade Separation (Burlington Northern and Santa Fe Railroad)
|
Riverside | $50,606 | $16,670 | Dec 01, 2013 | Jun 01, 2016 | |
Magnolia Avenue Grade Separation (Union Pacific Railroad)
|
Riverside | $50,248 | $17,288 | Feb 01, 2010 | Jan 01, 2012 | |
March Inland Cargo Port Airport (I-215 and Van Buren Boulevard Ground Access Improvements)
|
Riverside | 215 | $66,776 | $8,835 | Apr 30, 2012 | Apr 30, 2014 |
Riverside Avenue Grade Separation
|
Riverside | $31,784 | $10,064 | Oct 01, 2013 | Apr 01, 2015 | |
Streeter Avenue Grade Separation
|
Riverside | $36,000 | $15,500 | Nov 30, 2012 | May 30, 2014 | |
Sunset Avenue Grade Separation
|
Riverside | $33,042 | $8,278 | Dec 01, 2013 | Feb 28, 2016 | |
Metro Air Parkway Northbound Auxiliary Lane
|
Sacramento | 5 | $4 | $2 | Dec 15, 2020 | Dec 15, 2021 |
Natoma Overhead Widening and On Ramp Improvements
|
Sacramento | 50 | $8,459 | $7,959 | Dec 01, 2014 | Dec 01, 2015 |
SR99 Auxiliary Lanes Project
|
Sacramento | 99 | $7,095 | $900 | Aug 20, 2018 | Dec 01, 2019 |
Sacramento Intermodal Track Relocation
|
Sacramento | 80 | $81,292 | $25,266 | Mar 31, 2011 | Jan 31, 2013 |
Colton Crossing Grade Separation Project
|
San Bernardino | $83,477 | $27,847 | Sep 30, 2011 | Mar 30, 2014 | |
Glen Helen Parkway Railroad Grade Separation
|
San Bernardino | $25,885 | $7,172 | Apr 05, 2013 | Aug 22, 2014 | |
Hellman Avenue Crossing Improvements
|
San Bernardino | $3,580 | $1,790 | Aug 01, 2016 | Dec 31, 2016 | |
I-10 Corridor Express Lanes Contract 1
|
San Bernardino | 10 | $809,618 | $4,973 | Jul 01, 2018 | Feb 01, 2024 |
I-10 Pepper Avenue Interchange
|
San Bernardino | $10,111 | $1,158 | Oct 07, 2015 | Aug 17, 2017 | |
I-10 and Cherry Avenue Interchange Reconstruction
|
San Bernardino | 10 | $77,137 | $28,622 | Aug 01, 2011 | Dec 31, 2013 |
I-10 and Riverside Avenue Interchange Reconstruction
|
San Bernardino | 10 | $29,741 | $9,837 | Jan 01, 2010 | Jan 01, 2012 |
Laurel Street Grade Separation (Burlington Northern and Santa Fe Railroad)
|
San Bernardino | $58,218 | $22,825 | Sep 04, 2013 | Sep 06, 2015 | |
Lenwood Road Grade Separation
|
San Bernardino | 66 | $28,595 | $7,311 | Sep 13, 2013 | Oct 01, 2015 |
Monte Vista Grade Separation at UPRR Line
|
San Bernardino | $24,139 | $1,019 | Feb 07, 2017 | May 01, 2019 | |
Palm Avenue Railroad Grade Separation
|
San Bernardino | $23,780 | $1,877 | Jun 01, 2013 | Jun 30, 2015 | |
SR-60 Archilabd Ave Interchange Improvement
|
San Bernardino | 60 | $17,216 | $1,310 | Oct 28, 2019 | Mar 01, 2021 |
South Milliken Avenue Grade Separation at Union Pacific Los Angeles Subdivision
|
San Bernardino | $62,710 | $20,633 | Dec 11, 2013 | Jun 01, 2016 | |
State Route 60/Central Avenue Interchange
|
San Bernardino | 60 | $33 | $9 | Sep 02, 2020 | Apr 27, 2023 |
Tippecanoe Interchange Improvements, Phase II
|
San Bernardino | $56,279 | $8,691 | Aug 06, 2014 | Feb 01, 2017 | |
10th Avenue at Harbor Drive Grade Separation Improvements
|
San Diego | $3,954 | $598 | Nov 07, 2013 | Aug 25, 2016 | |
Bay Marina Drive at I-5 At-Grade Improvement
|
San Diego | 5 | $2,603 | $792 | Jun 14, 2012 | Nov 07, 2013 |
Civic Center Drive at Harbor Drive and I-5 At-Grade Improvements
|
San Diego | 5 | $1,731 | $361 | Jun 14, 2012 | Nov 07, 2013 |
LOSSAN North Rail Corridor (Sorrento to Miramar Double Track Project) Phase I
|
San Diego | $39,000 | $10,800 | Sep 01, 2011 | Sep 30, 2014 | |
Route 125/905 Connector
|
San Diego | 905, 125 | $29 | $24 | Aug 17, 2020 | Aug 15, 2022 |
SR-905/SR-125 Northbound Connectors
|
San Diego | 905, 125, 11 | $18,759 | $13,719 | Jul 01, 2015 | Oct 19, 2016 |
San Elijo Lagoon Double Track
|
San Diego | $70,254 | $4,343 | Sep 16, 2016 | Sep 16, 2018 | |
Sorrento Valley Double Track Project
|
San Diego | $34,810 | $12,994 | Nov 01, 2013 | Nov 01, 2015 | |
Southline Rail Improvement Project (Mainline Improvements)
|
San Diego | $48,504 | $39,534 | Jun 02, 2010 | Jul 01, 2015 | |
Southline Rail Improvements (San Ysidro Yard Expansion Project)
|
San Diego | $40,460 | $25,900 | Jan 04, 2013 | Jan 01, 2015 | |
State Route 11 and Otay Mesa East Port of Entry
|
San Diego | 11 | $685,893 | $74,155 | Jul 15, 2013 | Jun 30, 2016 |
State Route 905
|
San Diego | 905 | $82,953 | $66,804 | Jul 13, 2009 | Jul 11, 2012 |
Navy Drive Widening
|
San Joaquin | $6,813 | $2,000 | Jul 01, 2016 | Oct 01, 2017 | |
San Francisco Bay to Stockton Ship Channel Deepening Project
|
San Joaquin | 4 | $15,000 | $7,200 | Aug 01, 2012 | Nov 30, 2013 |
Southbound State Route 99 from Hammer Lane to Fremont Street Interchange Ramp Meterin
|
San Joaquin | $2,000 | $2,000 | Jun 24, 2015 | Jul 24, 2016 | |
Sperry Road Extension Project
|
San Joaquin | $56,582 | $23,582 | Jul 01, 2011 | Aug 01, 2013 | |
State Route 4 (West Crosstown Freeway Extension) Phase I
|
San Joaquin | 4 | $138,316 | $69,458 | Nov 01, 2013 | Dec 01, 2016 |
State Route 99 Ramp Improvements
|
San Joaquin | 99 | $2,973 | $2,333 | Aug 18, 2014 | Aug 18, 2015 |
US-101 Freeway Performance Initiative
|
Santa Clara | $24,764 | $13,840 | Sep 03, 2013 | Oct 24, 2014 | |
Fairfield/Vacaville Intermodal Station Segment No. 2C
|
Solano | $22,600 | $11,000 | Dec 02, 2014 | Nov 01, 2016 | |
I-80 Eastbound Cordelia Truck Scales Relocation
|
Solano | 80 | $88,392 | $38,292 | Aug 31, 2012 | Dec 31, 2014 |
Solano I-80/680/12 Connector
|
Solano | 80, 12 | $101,580 | $22,847 | Sep 30, 2013 | Jan 31, 2016 |
US-101 Marin Sonoma Narrows HOV Lane Project Phase 2
|
Sonoma | 101 | $37,662 | $3,000 | Mar 06, 2018 | Dec 31, 2019 |
Hueneme Road Widening
|
Ventura | $2,924 | $1,462 | Feb 15, 2013 | Feb 15, 2014 | |
Route 101 Improvements
|
Ventura | 101 | $46,525 | $10,346 | Aug 12, 2013 | Aug 10, 2015 |
US 101 Rice Avenue Interchange
|
Ventura | 101 | $73,597 | $14,194 | Oct 20, 2009 | Sep 30, 2012 |
West Sacramento Rail Plan
|
Yolo | $22,525 | $9,678 | Jul 11, 2011 | Dec 31, 2014 | |
SR70 / Feather River Blvd Interchange
|
Yuba | $19,350 | $4,361 | Apr 01, 2014 | Nov 30, 2015 | |
Total | $10,247,602 | $2,447,072 |
* Represent total bond funds planned