Caltrans Logo

Proposition 1B - Trade Corridors Improvement Fund

Title County State
Route
Total Project
Cost
(x1000)
Total
Bond
Funding*
(x1000)
Planned
Construction
Start
Planned
Construction
Finish
Cool Port Oakland
Alameda N/A $91,905 $5,000 Aug 01, 2016 Oct 01, 2017
I-580 Truck Climbing Lane
Alameda 580 $44,903 $44,903 Jun 01, 2012 Apr 01, 2015
I-880 Reconstruction (29th and 23rd Avenues)
Alameda 880 $97,912 $73,000 Jul 31, 2013 Jul 31, 2017
Outer Harbor Intermodal Terminal
Alameda $499,241 $242,141 Jan 01, 2010 Dec 31, 2019
Marina Bay Parkway Grade Separation
Contra Costa $42,180 $18,975 Feb 01, 2013 May 01, 2015
Richmond Rail Connector
Contra Costa $21,324 $9,555 Dec 31, 2013 Oct 31, 2015
Brawley Bypass (State Route 78 and 111 Expressway) Stage 3
Imperial 78 $69,334 $42,572 Nov 30, 2010 Mar 31, 2014
Tehachapi Trade Corridor Project
Kern 58 $26,040 $12,270 Sep 24, 2014 Oct 01, 2016
Alameda Corridor West Terminus Intermodal Railyard-West Basin Railyard Extension
Los Angeles $72,987 $20,712 Nov 21, 2013 Feb 28, 2016
Baldwin Avenue Grade Separation
Los Angeles $71,571 $27,739 Aug 31, 2012 Aug 31, 2014
C Street Access Ramps Improvement
Los Angeles 110 $38,427 $7,836 Nov 01, 2013 Oct 31, 2016
Cargo Transportation Improvement Emission Reduction Program
Los Angeles $147,250 $35,665 Jan 31, 2013 Sep 30, 2017
Citrus Avenue Crossing Improvements
Los Angeles $3,485 $1,455 Oct 30, 2016 Apr 30, 2018
Control Point Soledad Speed Increase
Los Angeles $6,648 $2,708 Oct 01, 2016 Apr 30, 2018
Durfee Avenue Grade Separation Project
Los Angeles $91,143 $2,620 Oct 31, 2018 Jul 31, 2021
Everport Terminal Berth Efficiency and Emission Reduction Project
Los Angeles $21,967 $5,430 May 19, 2019 Jun 07, 2021
Fairway Drive Grade Separation
Los Angeles $142,213 $71,000 Dec 31, 2014 Jun 30, 2018
Fullerton Road Grade Separation
Los Angeles $113,604 $35,060 Mar 30, 2016 Dec 30, 2019
Gateway (Valley View Grade Separation)
Los Angeles $63,997 $18,012 May 31, 2012 Aug 31, 2014
Gerald Desmond Bridge Replacement
Los Angeles 710 $1,336,061 $299,795 Jun 07, 2013 Jun 27, 2016
I-110 Freeway Access Ramp State Route 47 and 110 Northbound Connector Widening
Los Angeles 47, 110, 110 $40,773 $13,205 Jun 30, 2013 Jun 30, 2015
Middle Harbor Terminal Redeveloment
Los Angeles N/A $156,355 $15,436 Dec 01, 2017 Sep 30, 2020
New Freight Siding Antelope Valley Line
Los Angeles $11,163 $4,771 Aug 27, 2010 Mar 30, 2011
Ports Rail System Tier 1 (West Basin Rail Access Improvements
Los Angeles $135,097 $50,141 Jun 01, 2012 Jul 01, 2014
Ports Rail System Tier I (Pier F Support Yard)
Los Angeles $29,142 $4,093 Nov 29, 2012 May 15, 2014
Ports Rail System Tier I (Track Realignment at Ocean Boulevard)
Los Angeles $55,540 $16,216 Nov 29, 2012 May 15, 2014
Puente Avenue Grade Separation Project
Los Angeles $99,019 $48,000 Sep 30, 2014 Sep 30, 2017
Ramona Boulevard Crossing Improvements
Los Angeles $3,485 $1,455 Oct 30, 2016 Apr 30, 2018
San Gabriel Valley Grade Separation Program
Los Angeles $595,510 $237,778 Jun 30, 2004 Sep 30, 2017
South Wilmington Grade Separation
Los Angeles $73,582 $13,759 Nov 01, 2012 Nov 01, 2014
TraPac Terminal Automation - Automated Shuttle Carrier Maintenance & Repair (M&R) Facility
Los Angeles $5,681 $2,840 Jul 31, 2015 Aug 31, 2016
Vincent Siding at CP Quartz and 2nd Platform at Vincent/Acton Grade Station
Los Angeles $17,400 $8,200 Apr 30, 2015 Dec 31, 2016
Washington Boulevard Widening and Reconstruction Project
Los Angeles $32,000 $5,800 Dec 15, 2014 Mar 01, 2016
YTI Terminal Enhancement & Truck Trip Reduction Program
Los Angeles $51,198 $9,533 Jul 14, 2015 May 12, 2017
Sanborn Rd/US101 Interchange Improvements and Elvee Drive Extension
Monterey $4,300 $1,700 May 26, 2015 May 26, 2016
I-405 HOV Lane
Orange 405 $1,506,136 $7,771 Jan 31, 2017 Aug 31, 2026
I-5 Improvement from SR-73 to Oso Parkway (Segment 1)
Orange 5 $179,768 $26,991 Oct 01, 2019 Jan 01, 2024
Kraemer Blvd Undercrossing
Orange $53,185 $15,513 Oct 01, 2011 May 01, 2014
Lakeview Avenue Overcrossing
Orange $91,149 $27,520 Sep 01, 2013 Dec 01, 2015
Orangethorpe Avenue Grade Separation
Orange $95,325 $30,324 Mar 01, 2013 Jul 01, 2016
Placentia Avenue Undercrossing
Orange $56,794 $9,548 Oct 01, 2011 May 01, 2014
Raymond Avenue Grade Separation
Orange $110,700 $10,400 Jul 29, 2014 Jul 15, 2018
State College Grade Separation
Orange $71,554 $32,800 Nov 01, 2013 Aug 01, 2016
State Route 91 (Auxiliary Lanes on Westbound State Route 91 between State Route 57 and I-5)
Orange 91 $44,268 $25,438 Dec 01, 2012 Dec 01, 2015
Tustin Avenue and Rose Drive Overcrossing
Orange $86,381 $30,862 Mar 01, 2013 Sep 01, 2015
I-80/SR-65 Interchange Phase I-Third Lane Project
Placer 65 $43,053 $3,600 Nov 14, 2017 Nov 01, 2020
ACE: Avenue 66/UP Railroad Grade Separation Bypass
Riverside N/A $39,080 $5,709 Jul 30, 2019 Jul 29, 2021
Auto Center Drive Grade Separation
Riverside $32,675 $16,000 Nov 01, 2011 Apr 30, 2013
Avenue 52 Grade Separation Project
Riverside $33,516 $9,766 Oct 15, 2013 Mar 31, 2015
Avenue 56 Grade Separation Union Pacific Yuma Subdivision
Riverside $29,394 $12,802 Dec 01, 2013 Feb 28, 2016
Clay Street Grade Separation
Riverside $30,806 $13,247 Dec 01, 2013 Jun 15, 2016
Columbia Avenue Grade Separation
Riverside $33,003 $4,953 Sep 01, 2008 Dec 01, 2009
Iowa Avenue Grade Separation
Riverside $32,000 $13,000 Jun 26, 2012 Nov 01, 2013
Magnolia Avenue Grade Separation (Burlington Northern and Santa Fe Railroad)
Riverside $50,606 $16,670 Dec 01, 2013 Jun 01, 2016
Magnolia Avenue Grade Separation (Union Pacific Railroad)
Riverside $50,248 $17,288 Feb 01, 2010 Jan 01, 2012
March Inland Cargo Port Airport (I-215 and Van Buren Boulevard Ground Access Improvements)
Riverside 215 $66,776 $8,835 Apr 30, 2012 Apr 30, 2014
Riverside Avenue Grade Separation
Riverside $31,784 $10,064 Oct 01, 2013 Apr 01, 2015
Streeter Avenue Grade Separation
Riverside $36,000 $15,500 Nov 30, 2012 May 30, 2014
Sunset Avenue Grade Separation
Riverside $33,042 $8,278 Dec 01, 2013 Feb 28, 2016
Metro Air Parkway Northbound Auxiliary Lane
Sacramento 5 $4 $2 Dec 15, 2020 Dec 15, 2021
Natoma Overhead Widening and On Ramp Improvements
Sacramento 50 $8,459 $7,959 Dec 01, 2014 Dec 01, 2015
SR99 Auxiliary Lanes Project
Sacramento 99 $7,095 $900 Aug 20, 2018 Dec 01, 2019
Sacramento Intermodal Track Relocation
Sacramento 80 $81,292 $25,266 Mar 31, 2011 Jan 31, 2013
Colton Crossing Grade Separation Project
San Bernardino $83,477 $27,847 Sep 30, 2011 Mar 30, 2014
Glen Helen Parkway Railroad Grade Separation
San Bernardino $25,885 $7,172 Apr 05, 2013 Aug 22, 2014
Hellman Avenue Crossing Improvements
San Bernardino $3,580 $1,790 Aug 01, 2016 Dec 31, 2016
I-10 Corridor Express Lanes Contract 1
San Bernardino 10 $809,618 $4,973 Jul 01, 2018 Feb 01, 2024
I-10 Pepper Avenue Interchange
San Bernardino $10,111 $1,158 Oct 07, 2015 Aug 17, 2017
I-10 and Cherry Avenue Interchange Reconstruction
San Bernardino 10 $77,137 $28,622 Aug 01, 2011 Dec 31, 2013
I-10 and Riverside Avenue Interchange Reconstruction
San Bernardino 10 $29,741 $9,837 Jan 01, 2010 Jan 01, 2012
Laurel Street Grade Separation (Burlington Northern and Santa Fe Railroad)
San Bernardino $58,218 $22,825 Sep 04, 2013 Sep 06, 2015
Lenwood Road Grade Separation
San Bernardino 66 $28,595 $7,311 Sep 13, 2013 Oct 01, 2015
Monte Vista Grade Separation at UPRR Line
San Bernardino $24,139 $1,019 Feb 07, 2017 May 01, 2019
Palm Avenue Railroad Grade Separation
San Bernardino $23,780 $1,877 Jun 01, 2013 Jun 30, 2015
SR-60 Archilabd Ave Interchange Improvement
San Bernardino 60 $17,216 $1,310 Oct 28, 2019 Mar 01, 2021
South Milliken Avenue Grade Separation at Union Pacific Los Angeles Subdivision
San Bernardino $62,710 $20,633 Dec 11, 2013 Jun 01, 2016
State Route 60/Central Avenue Interchange
San Bernardino 60 $33 $9 Sep 02, 2020 Apr 27, 2023
Tippecanoe Interchange Improvements, Phase II
San Bernardino $56,279 $8,691 Aug 06, 2014 Feb 01, 2017
10th Avenue at Harbor Drive Grade Separation Improvements
San Diego $3,954 $598 Nov 07, 2013 Aug 25, 2016
Bay Marina Drive at I-5 At-Grade Improvement
San Diego 5 $2,603 $792 Jun 14, 2012 Nov 07, 2013
Civic Center Drive at Harbor Drive and I-5 At-Grade Improvements
San Diego 5 $1,731 $361 Jun 14, 2012 Nov 07, 2013
LOSSAN North Rail Corridor (Sorrento to Miramar Double Track Project) Phase I
San Diego $39,000 $10,800 Sep 01, 2011 Sep 30, 2014
Route 125/905 Connector
San Diego 905, 125 $29 $24 Aug 17, 2020 Aug 15, 2022
SR-905/SR-125 Northbound Connectors
San Diego 905, 125, 11 $18,759 $13,719 Jul 01, 2015 Oct 19, 2016
San Elijo Lagoon Double Track
San Diego $70,254 $4,343 Sep 16, 2016 Sep 16, 2018
Sorrento Valley Double Track Project
San Diego $34,810 $12,994 Nov 01, 2013 Nov 01, 2015
Southline Rail Improvement Project (Mainline Improvements)
San Diego $48,504 $39,534 Jun 02, 2010 Jul 01, 2015
Southline Rail Improvements (San Ysidro Yard Expansion Project)
San Diego $40,460 $25,900 Jan 04, 2013 Jan 01, 2015
State Route 11 and Otay Mesa East Port of Entry
San Diego 11 $685,893 $74,155 Jul 15, 2013 Jun 30, 2016
State Route 905
San Diego 905 $82,953 $66,804 Jul 13, 2009 Jul 11, 2012
Navy Drive Widening
San Joaquin $6,813 $2,000 Jul 01, 2016 Oct 01, 2017
San Francisco Bay to Stockton Ship Channel Deepening Project
San Joaquin 4 $15,000 $7,200 Aug 01, 2012 Nov 30, 2013
Southbound State Route 99 from Hammer Lane to Fremont Street Interchange Ramp Meterin
San Joaquin $2,000 $2,000 Jun 24, 2015 Jul 24, 2016
Sperry Road Extension Project
San Joaquin $56,582 $23,582 Jul 01, 2011 Aug 01, 2013
State Route 4 (West Crosstown Freeway Extension) Phase I
San Joaquin 4 $138,316 $69,458 Nov 01, 2013 Dec 01, 2016
State Route 99 Ramp Improvements
San Joaquin 99 $2,973 $2,333 Aug 18, 2014 Aug 18, 2015
US-101 Freeway Performance Initiative
Santa Clara $24,764 $13,840 Sep 03, 2013 Oct 24, 2014
Fairfield/Vacaville Intermodal Station Segment No. 2C
Solano $22,600 $11,000 Dec 02, 2014 Nov 01, 2016
I-80 Eastbound Cordelia Truck Scales Relocation
Solano 80 $88,392 $38,292 Aug 31, 2012 Dec 31, 2014
Solano I-80/680/12 Connector
Solano 80, 12 $101,580 $22,847 Sep 30, 2013 Jan 31, 2016
US-101 Marin Sonoma Narrows HOV Lane Project Phase 2
Sonoma 101 $37,662 $3,000 Mar 06, 2018 Dec 31, 2019
Hueneme Road Widening
Ventura $2,924 $1,462 Feb 15, 2013 Feb 15, 2014
Route 101 Improvements
Ventura 101 $46,525 $10,346 Aug 12, 2013 Aug 10, 2015
US 101 Rice Avenue Interchange
Ventura 101 $73,597 $14,194 Oct 20, 2009 Sep 30, 2012
West Sacramento Rail Plan
Yolo $22,525 $9,678 Jul 11, 2011 Dec 31, 2014
SR70 / Feather River Blvd Interchange
Yuba $19,350 $4,361 Apr 01, 2014 Nov 30, 2015
Total $10,247,602 $2,447,072    

* Represent total bond funds planned