Caltrans Logo

Proposition 1B - Highway-Railroad Crossing Safety

Title County Total Project
Cost
(x1000)
Total
Bond
Funding*
(x1000)
Planned
Construction
Start
Planned
Construction
Finish
Kato Road Grade Separation
Alameda $48,809 $9,124 Aug 30, 2011 Dec 30, 2012
Warren Avenue Grade Separation
Alameda $66,994 $7,812 Jun 25, 2012 Jun 25, 2015
Officer Bradley A. Moody Memorial Underpass
Contra Costa $41,925 $3,975 Feb 01, 2013 May 01, 2015
BNSF Grade Separation at 7th Standard Rd/Santa Fe Way
Kern $21,928 $7,044 Apr 10, 2010 Jul 01, 2011
Hageman Road/BNSF Railroad Grade Separation
Kern $31,409 $13,759 Dec 15, 2010 Jul 30, 2012
Branford Street Grade Crossing Safety Improvement
Los Angeles $2,943 $1,220 Apr 02, 2014 Dec 30, 2016
Broadway-Brazil Street Grade Crossing Improvements
Los Angeles $4,738 $233 Jul 13, 2011 Aug 13, 2012
Durfee Avenue Grade Separation
Los Angeles $91,143 $2,706 Apr 01, 2018 Oct 31, 2020
Fullerton Road Grade Separation Project
Los Angeles $153,184 $18,306 Mar 01, 2016 Sep 30, 2019
Grandview Avenue Grade Crossing Safety Improvements
Los Angeles $2,630 $580 Mar 31, 2013 Aug 30, 2013
Nogales Street Grade Separation
Los Angeles $116,801 $25,600 Dec 15, 2012 Dec 15, 2015
North Spring Street Grade Separation Reconstruction
Los Angeles $48,758 $4,993 Dec 31, 2012 Jun 30, 2015
Riverside Drive Grade Separation Replacement
Los Angeles $57,725 $5,000 Jun 30, 2011 Jun 30, 2015
Sonora Avenue Grade Crossing Safety Improvement
Los Angeles $2,692 $580 Sep 30, 2012 Feb 27, 2013
Woodley Avenue Grade Crossing
Los Angeles $938 $438 Dec 01, 2014 Aug 28, 2017
G Street Undercrossing
Merced $16,413 $7,413 Jun 15, 2010 Dec 15, 2011
Dana Point and San Clemente Crossings
Orange $4,200 $2,100 Nov 01, 2011 Jun 01, 2012
San Clemente Beach Trail Crossings
Orange $4,420 $2,170 Sep 01, 2012 Mar 01, 2013
Sand Canyon Grade Separation
Orange $55,590 $6,618 Apr 30, 2011 Jan 30, 2014
McKinley Street Grade Separation
Riverside $128,447 $2,876 Sep 01, 2021 Jun 30, 2023
6th Street Overcrossing - Bridge
Sacramento $10,824 $4,837 Apr 30, 2011 Oct 31, 2012
6th Street Overcrossing - Roadwork
Sacramento $15,016 $7,151 Dec 08, 2012 Jun 28, 2015
Grant Line Road Grade Separation with UPPR
Sacramento $28,531 $3,156 Feb 27, 2013 Apr 30, 2015
Park Boulevard at Harbor Drive Pedestrian Bridge
San Diego $27,000 $6,000 Jun 26, 2008 Jan 01, 2010
Jerrold Avenue Bridge Grade Separation
San Francisco $11,582 $2,668 Jun 03, 2010 Sep 03, 2011
Eight Mile Road/UPRR (East) Grade Separation
San Joaquin $27,780 $5,280 Oct 01, 2010 May 07, 2014
Eight Mile Road/UPRR (West) Grade Separation
San Joaquin $23,924 $7,424 Oct 01, 2010 May 07, 2014
Lathrop Road
San Joaquin $16,855 $5,000 Aug 05, 2013 Oct 01, 2015
Lower Sacramento Road at UPRR Grade Separation
San Joaquin $30,824 $6,484 Oct 01, 2010 Nov 01, 2012
Navy Drive/BNSF Underpass Part 1 & 2
San Joaquin $9,097 $5,740 Mar 14, 2014 Aug 01, 2015
Port of Stockton Expressway
San Joaquin $8,587 $1,537 Apr 15, 2011 Jun 30, 2011
San Bruno Grade Separation
San Mateo $147,050 $26,727 Jul 01, 2010 Oct 31, 2012
San Mateo Bridges GS P2
San Mateo $28,192 $8,864 May 08, 2014 May 30, 2016
San Mateo Bridges Grade Separation
San Mateo $10,148 $955 Oct 07, 2010 Jun 30, 2011
Bardsley Avenue Grade Separation
Tulare $18,369 $7,027 Nov 15, 2012 Feb 28, 2015
Betty Drive Grade Separation
Tulare $14,294 $4,855 Dec 20, 2010 Jun 01, 2011
Cartmill Avenue Grade Separation
Tulare $25,566 $10,051 Dec 01, 2010 May 31, 2012
Santa Fe Trail
Tulare $7,363 $3,931 Feb 01, 2014 Dec 31, 2014
Moorpark Avenue Grade Crossing Safety Improvement
Ventura $5,012 $4,812 Jul 31, 2013 Dec 31, 2013
Total $1,367,701 $245,046    

* Represent total bond funds planned