Vehicle Detection for CMIA Cooridors

Description: In El Dorado, Placer, Sacramento and Yolo Counties on Routes 50, 65 and 80. Install Vehicle Detection Systems along CMIA corridors. (Prop 1B Bond Funded Project)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento, El Dorado, Placer, Yolo
City Sacramento
Zip Code 95619, 95667, 95823
 
Senate District
01, 06
Assembly District 05, 10
Congressional District 03, 05
 
Caltrans District
03
 
 
County/State Route Sacramento 50
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      0.25  
Lane Miles Added (HOV)      0  
Lane Miles Added (Mixed)      0  
Number of Stations / Number of Ramps Metered  65    53  
Peak Period Time Savings (minutes)      15  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Brian Simi (916) 859-7960   brian.simi@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Brian Simi (916) 859-7960   brian.simi@dot.ca.gov
Right of Way Phase
Department of Transportation Brian Simi (916) 859-7960   brian.simi@dot.ca.gov
Construction Phase
Department of Transportation Brian Simi (916) 859-7960   brian.simi@dot.ca.gov
 
Corridor System Management Plan
Department of Transportation Brian Simi (916) 859-7960   brian.simi@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$3,276 $0 $3,276
Non-bond Funding
State/Federal*
$0 $0 $0
 
Total**** $3,276 $0 $3,276

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$30 $0 $30 $3
Design(PS&E)
$80 $0 $80 $122
Right of Way
$20 $0 $20 $6
Construction
$3,146 $0 $3,146 $1,885
 
Total* $3,276 $0 $3,276 $2,016

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

08/15/2007 
 

 
 

08/15/2007 
100   

08/15/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

10/15/2007 
 

 
 

10/15/2007 
100   

09/17/2007 


Begin Right of Way Phase

End Right of Way Phase
 

10/01/2007 
 

 
 

10/01/2007 
100   

08/15/2007 


Begin Construction Phase

End Construction Phase
02/01/2008 

11/01/2008 
06/07/2007 

11/13/2008 
02/01/2008 

11/01/2008 
100  01/24/2008 

11/13/2008 


Begin Closeout Phase

End Closeout Phase
11/01/2008 

10/01/2010 
 

 
11/01/2008 

10/01/2010 
100  11/14/2008 

10/20/2010 


-1 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 0.25
Lane Miles Added (HOV) 0
Lane Miles Added (Mixed) 0
Number of Stations / Number of Ramps Metered 65 53
Peak Period Time Savings (minutes) 15

Bond Funding Cost
Adopted:
$3,276,000
Current Approved:
$3,276,000
Actual Expenditures:
$2,100,000

 

Status as of December 31, 2023.