Vehicle Detection for CMIA Cooridors |
Description: In El Dorado, Placer, Sacramento and Yolo Counties on Routes 50, 65 and 80. Install Vehicle Detection Systems along CMIA corridors. (Prop 1B Bond Funded Project)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Sacramento, El Dorado, Placer, Yolo |
City | Sacramento |
Zip Code | 95619, 95667, 95823 |
Senate District |
01, 06 |
Assembly District | 05, 10 |
Congressional District | 03, 05 |
Caltrans District |
03 |
County/State Route | Sacramento 50 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 0.25 | |
Lane Miles Added (HOV) | 0 | |
Lane Miles Added (Mixed) | 0 | |
Number of Stations / Number of Ramps Metered | 65 | 53 |
Peak Period Time Savings (minutes) | 15 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Brian Simi | (916) 859-7960 | brian.simi@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | Brian Simi | (916) 859-7960 | brian.simi@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | Brian Simi | (916) 859-7960 | brian.simi@dot.ca.gov | |
Construction Phase |
Department of Transportation | Brian Simi | (916) 859-7960 | brian.simi@dot.ca.gov | |
Corridor System Management Plan |
Department of Transportation | Brian Simi | (916) 859-7960 | brian.simi@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SHOPP Augmentation |
$3,276 | $0 | $3,276 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Total**** | $3,276 | $0 | $3,276 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$30 | $0 | $30 | $3 | |||
Design(PS&E) |
$80 | $0 | $80 | $122 | |||
Right of Way |
$20 | $0 | $20 | $6 | |||
Construction |
$3,146 | $0 | $3,146 | $1,885 | |||
Total* | $3,276 | $0 | $3,276 | $2,016 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
08/15/2007 |
|
08/15/2007 |
100 | 08/15/2007 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/15/2007 |
|
10/15/2007 |
100 | 09/17/2007 |
0 1 |
Begin Right of Way Phase
End Right of Way Phase |
10/01/2007 |
|
10/01/2007 |
100 | 08/15/2007 |
0 2 |
Begin Construction Phase
End Construction Phase |
02/01/2008 11/01/2008 |
06/07/2007 11/13/2008 |
02/01/2008 11/01/2008 |
100 | 01/24/2008 11/13/2008 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
11/01/2008 10/01/2010 |
|
11/01/2008 10/01/2010 |
100 | 11/14/2008 10/20/2010 |
0 -1 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 0.25 | |
Lane Miles Added (HOV) | 0 | |
Lane Miles Added (Mixed) | 0 | |
Number of Stations / Number of Ramps Metered | 65 | 53 |
Peak Period Time Savings (minutes) | 15 |
Bond Funding Cost | |
---|---|
Adopted: |
$3,276,000 |
Current Approved: |
$3,276,000 |
Actual Expenditures: |
$2,100,000 |
Status as of December 31, 2023.