Description: Near Truckee, from 0.1 mile west of Donner Summit to 1.2 miles west of Donner Park overcrossing. Rehabilitate pavement. (Prop 1B Bond Funded Project)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Nevada |
City | Truckee |
Zip Code | 96161 |
Senate District |
01 |
Assembly District | 03 |
Congressional District | 04 |
Caltrans District |
03 |
County/State Route | Nevada 80 |
Postmile Begin/End | R 5.2 R 11.3 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Distress Pavement Lane Miles Retired | 15 | |
Pavement Lane Miles | 23 | |
Peak Period Time Savings (minutes) | 23 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Jonathan Pray | 530-740-4920 | jonathan.pray@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | Jonathan Pray | 530-740-4920 | jonathan.pray@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | Jonathan Pray | 530-740-4920 | jonathan.pray@dot.ca.gov | |
Construction Phase |
Department of Transportation | Jonathan Pray | 530-740-4920 | jonathan.pray@dot.ca.gov | |
Corridor System Management Plan |
Department of Transportation | Jonathan Pray | 530-740-4920 | jonathan.pray@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SHOPP Augmentation |
$0 | $90,400 | $90,400 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $100 | $100 | ||||
Total**** | $0 | $90,500 | $90,500 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$0 | $100 | $100 | $0 | |||
Design(PS&E) |
$0 | $1,000 | $1,000 | $946 | |||
Right of Way |
$0 | $200 | $200 | $138 | |||
Construction |
$0 | $89,200 | $89,200 | $67,197 | |||
Total* | $0 | $90,500 | $90,500 | $68,281 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/01/2007 10/01/2007 |
|
07/01/2007 10/01/2007 |
100 | 05/29/2007 06/07/2007 |
1 4 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2007 04/01/2008 |
|
07/01/2007 04/01/2008 |
100 | 07/01/2007 04/15/2008 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
07/01/2007 04/01/2008 |
|
07/01/2007 04/01/2008 |
100 | 04/01/2007 03/06/2008 |
3 1 |
Begin Construction Phase
End Construction Phase |
10/01/2008 01/01/2012 |
|
10/01/2008 01/01/2012 |
100 | 07/28/2008 01/15/2012 |
2 0 |
Begin Closeout Phase
End Closeout Phase |
01/01/2013 01/01/2014 |
|
01/01/2013 01/01/2014 |
50 | 01/15/2012 12/19/2019 |
12 -73 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Distress Pavement Lane Miles Retired | 15 | |
Pavement Lane Miles | 23 | |
Peak Period Time Savings (minutes) | 23 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$90,500,000 |
Actual Expenditures: |
$68,023,000 |
Status as of December 31, 2023.