Ramp Metering Improvements at Rte 50/Folsom Blvd

Description: In Sacramento, at the Folsom Boulevard Interchange. Install ramp metering. (Prop 1B Bond Funded Project)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City Sacramento
Zip Code 95826
 
Senate District
01, 06
Assembly District 05, 10
Congressional District 03, 05
 
Caltrans District
03
 
 
County/State Route Sacramento 50
Postmile Begin/End 17 17.5
Project Benefits
 Benefit Baseline Actual
Number of Stations / Number of Ramps Metered  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Clark Peri (916) 274-0538   cperi@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Clark Peri (916) 274-0538   cperi@dot.ca.gov
Right of Way Phase
Department of Transportation Clark Peri (916) 274-0538   cperi@dot.ca.gov
Construction Phase
Department of Transportation Clark Peri (916) 274-0538   cperi@dot.ca.gov
 
Corridor System Management Plan
Department of Transportation Clark Peri (916) 274-0538   cperi@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$5,360 $-2,532 $2,828
Non-bond Funding
State/Federal*
$24,780 $-11,878 $12,902
Non Budgeted ETC
$0 $0 $0
 
Total**** $30,140 $-14,410 $15,730

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$2,168 $-1,168 $1,000 $959
Design(PS&E)
$2,500 $-500 $2,000 $1,948
Right of Way
$545 $-115 $430 $42
Construction
$24,927 $-12,627 $12,300 $6,774
 
Total* $30,140 $-14,410 $15,730 $9,723

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2007 

01/01/2009 
 

 
07/01/2007 

01/01/2009 
100  07/01/2007 

12/30/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2009 

02/01/2010 
 

 
01/01/2009 

02/01/2010 
100  01/01/2009 

01/19/2010 


Begin Right of Way Phase

End Right of Way Phase
02/01/2009 

02/01/2010 
 

 
02/01/2009 

02/01/2010 
100  10/01/2008 

01/12/2010 


Begin Construction Phase

End Construction Phase
06/01/2010 

11/01/2011 
 

 
08/25/2011 

08/01/2013 
100  07/22/2011 

12/12/2013 


-4 
Begin Closeout Phase

End Closeout Phase
11/01/2012 

11/01/2013 
 

 
08/01/2014 

08/01/2015 
50  12/12/2013 

08/01/2015 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Number of Stations / Number of Ramps Metered 1

Bond Funding Cost
Adopted:
$5,360,000
Current Approved:
$20,430,000
Actual Expenditures:
$9,173,000

 

Status as of December 31, 2023.