Ramp Metering Improvements at Rte 50/Folsom Blvd |
Description: In Sacramento, at the Folsom Boulevard Interchange. Install ramp metering. (Prop 1B Bond Funded Project)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Sacramento |
City | Sacramento |
Zip Code | 95826 |
Senate District |
01, 06 |
Assembly District | 05, 10 |
Congressional District | 03, 05 |
Caltrans District |
03 |
County/State Route | Sacramento 50 |
Postmile Begin/End | 17 17.5 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Clark Peri | (916) 274-0538 | cperi@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | Clark Peri | (916) 274-0538 | cperi@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | Clark Peri | (916) 274-0538 | cperi@dot.ca.gov | |
Construction Phase |
Department of Transportation | Clark Peri | (916) 274-0538 | cperi@dot.ca.gov | |
Corridor System Management Plan |
Department of Transportation | Clark Peri | (916) 274-0538 | cperi@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SHOPP Augmentation |
$5,360 | $-2,532 | $2,828 | ||||
Non-bond Funding | |||||||
State/Federal* |
$24,780 | $-11,878 | $12,902 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $30,140 | $-14,410 | $15,730 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$2,168 | $-1,168 | $1,000 | $959 | |||
Design(PS&E) |
$2,500 | $-500 | $2,000 | $1,948 | |||
Right of Way |
$545 | $-115 | $430 | $42 | |||
Construction |
$24,927 | $-12,627 | $12,300 | $6,774 | |||
Total* | $30,140 | $-14,410 | $15,730 | $9,723 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/01/2007 01/01/2009 |
|
07/01/2007 01/01/2009 |
100 | 07/01/2007 12/30/2008 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2009 02/01/2010 |
|
01/01/2009 02/01/2010 |
100 | 01/01/2009 01/19/2010 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
02/01/2009 02/01/2010 |
|
02/01/2009 02/01/2010 |
100 | 10/01/2008 01/12/2010 |
4 1 |
Begin Construction Phase
End Construction Phase |
06/01/2010 11/01/2011 |
|
08/25/2011 08/01/2013 |
100 | 07/22/2011 12/12/2013 |
1 -4 |
Begin Closeout Phase
End Closeout Phase |
11/01/2012 11/01/2013 |
|
08/01/2014 08/01/2015 |
50 | 12/12/2013 08/01/2015 |
8 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$5,360,000 |
Current Approved: |
$20,430,000 |
Actual Expenditures: |
$9,173,000 |
Status as of December 31, 2023.