Reconstruct Bay Bridge Toll Plaza maintenance facilities. |
Description: Near Oakland, at the San Francisco Oakland Bay Bridge Toll Plaza Building. Reconstruct maintenance facilities.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Alameda |
City | Oakland |
Zip Code | 94105 |
Senate District |
09 |
Assembly District | 16 |
Congressional District | 09 |
Caltrans District |
04 |
County/State Route | Alameda 80 |
Postmile Begin/End | 1.8 1.8 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | x |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Al Lee | (510) 715-8663 | al.b.lee@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | Al Lee | (510) 715-8663 | al.b.lee@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | Al Lee | (510) 715-8663 | al.b.lee@dot.ca.gov | |
Construction Phase |
Department of Transportation | Al Lee | (510) 715-8663 | al.b.lee@dot.ca.gov | |
Corridor System Management Plan |
Department of Transportation | Nidal Tuqan | (510)286-5542 | nidal.tuqan@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SHOPP Augmentation |
$500 | $0 | $500 | ||||
Non-bond Funding | |||||||
State/Federal* |
$7,524 | $3,417 | $10,941 | ||||
Local** |
$0 | $0 | $0 | ||||
Total**** | $8,024 | $3,417 | $11,441 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$656 | $0 | $656 | $340 | |||
Design(PS&E) |
$3,700 | $80 | $3,780 | $8,438 | |||
Right of Way |
$10 | $-5 | $5 | $235 | |||
Construction |
$3,658 | $3,342 | $7,000 | $26,264 | |||
Total* | $8,024 | $3,417 | $11,441 | $35,277 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | 02/01/2003 12/31/2005 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | 12/31/2005 03/28/2014 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | 02/01/2014 |
0 0 |
Begin Construction Phase
End Construction Phase |
|
|
09/15/2014 03/01/2016 |
0 | 07/29/2014 12/29/2017 |
2 -22 |
Begin Closeout Phase
End Closeout Phase |
|
|
|
0 | 09/08/2017 12/29/2018 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | x |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.