Reconstruct Bay Bridge Toll Plaza maintenance facilities.

Description: Near Oakland, at the San Francisco Oakland Bay Bridge Toll Plaza Building. Reconstruct maintenance facilities.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Oakland
Zip Code 94105
 
Senate District
09
Assembly District 16
Congressional District 09
 
Caltrans District
04
 
 
County/State Route Alameda 80
Postmile Begin/End 1.8 1.8
Project Benefits
 Benefit Baseline Actual
Increase in Throughput  x      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Al Lee (510) 715-8663   al.b.lee@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Al Lee (510) 715-8663   al.b.lee@dot.ca.gov
Right of Way Phase
Department of Transportation Al Lee (510) 715-8663   al.b.lee@dot.ca.gov
Construction Phase
Department of Transportation Al Lee (510) 715-8663   al.b.lee@dot.ca.gov
 
Corridor System Management Plan
Department of Transportation Nidal Tuqan (510)286-5542   nidal.tuqan@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$500 $0 $500
Non-bond Funding
State/Federal*
$7,524 $3,417 $10,941
Local**
$0 $0 $0
 
Total**** $8,024 $3,417 $11,441

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$656 $0 $656 $340
Design(PS&E)
$3,700 $80 $3,780 $8,438
Right of Way
$10 $-5 $5 $235
Construction
$3,658 $3,342 $7,000 $26,264
 
Total* $8,024 $3,417 $11,441 $35,277

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
02/01/2003 

12/31/2005 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
12/31/2005 

03/28/2014 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

02/01/2014 


Begin Construction Phase

End Construction Phase
 

 
 

 
09/15/2014 

03/01/2016 
07/29/2014 

12/29/2017 


-22 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
09/08/2017 

12/29/2018 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Throughput x

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.