Install 26 Miles of Fiber Optics Trunk Line, Hubs and TOS/TMS Elements |
Description: In Alameda, Contra Costa, and Solano Counties, on Routes 80, 580 and 980 at various locations. Install traffic operations systems (TOS).
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Alameda |
City | Alameda |
Zip Code | 94501 |
Senate District |
|
Assembly District | |
Congressional District | |
Caltrans District |
|
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Period Time Savings (minutes) | 10 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
|||||
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SHOPP Augmentation |
$0 | $0 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $110,996 | $110,996 | ||||
Total**** | $0 | $110,996 | $110,996 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$0 | $0 | $0 | $0 | |||
Design(PS&E) |
$0 | $6,200 | $6,200 | $0 | |||
Right of Way |
$0 | $441 | $441 | $0 | |||
Construction |
$0 | $104,355 | $104,355 | $0 | |||
Total* | $0 | $110,996 | $110,996 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
07/01/2014 10/15/2015 |
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
10/15/2015 04/03/2017 |
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
12/15/2015 10/02/2017 |
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
|
|
10/02/2017 12/13/2019 |
0 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
|
|
12/31/2019 12/31/2020 |
0 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Period Time Savings (minutes) | 10 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.