Install 26 Miles of Fiber Optics Trunk Line, Hubs and TOS/TMS Elements

Description: In Alameda, Contra Costa, and Solano Counties, on Routes 80, 580 and 980 at various locations. Install traffic operations systems (TOS).

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Alameda
Zip Code 94501
 
Senate District

Assembly District
Congressional District
 
Caltrans District

 
Project Benefits
 Benefit Baseline Actual
Peak Period Time Savings (minutes)  10      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
 
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$0 $0 $0
Non-bond Funding
State/Federal*
$0 $110,996 $110,996
 
Total**** $0 $110,996 $110,996

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$0 $0 $0 $0
Design(PS&E)
$0 $6,200 $6,200 $0
Right of Way
$0 $441 $441 $0
Construction
$0 $104,355 $104,355 $0
 
Total* $0 $110,996 $110,996 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
07/01/2014 

10/15/2015 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
10/15/2015 

04/03/2017 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
12/15/2015 

10/02/2017 
 

 


Begin Construction Phase

End Construction Phase
 

 
 

 
10/02/2017 

12/13/2019 
 

 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
12/31/2019 

12/31/2020 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Period Time Savings (minutes) 10

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.