Caltrans Logo

Traffic Detection Project

Description: In Alameda, Contra Costa, Marin, San Mateo, Santa Clara, Solano and Sonoma Counties on various routes. Install Vehicle Detection Systems (VDS). (Prop 1B Bond Funded Project)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City San Mateo, Santa Clara, Sonoma
Zip Code 94403, 95476
 
Senate District
02, 03, 05, 08, 09
Assembly District 01, 06, 07, 08, 11, 16, 19, 21, 27
Congressional District 01, 02, 03, 06, 07, 09, 11, 12, 14
 
Caltrans District
04
 
 
County/State Route Alameda 24
Postmile Begin/End 1.8 6.2
Project Benefits
 Benefit Baseline Actual
Number of Stations / Number of Ramps Metered  66      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Paul Mai (510) 622-0754   paul_mai@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Paul Mai (510) 622-0754   paul_mai@dot.ca.gov
Right of Way Phase
Department of Transportation Paul Mai (510) 622-0754   paul_mai@dot.ca.gov
Construction Phase
Department of Transportation Paul Mai (510) 622-0754   paul_mai@dot.ca.gov
 
Corridor System Management Plan
Department of Transportation Paul Mai (510) 622-0754   paul_mai@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$22,438 $-19,668 $2,770
Non-bond Funding
State/Federal*
$0 $0 $0
 
Total**** $22,438 $-19,668 $2,770

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,035 $-908 $127 $124
Design(PS&E)
$1,900 $-1,666 $234 $351
Right of Way
$173 $-152 $21 $0
Construction
$19,330 $-16,942 $2,388 $1,285
 
Total* $22,438 $-19,668 $2,770 $1,759

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

10/01/2007 
 

 
 

10/15/2007 
100   

10/15/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

01/21/2008 
 

 
 

01/21/2008 
100   

01/16/2008 


Begin Right of Way Phase

End Right of Way Phase
 

01/15/2008 
 

 
 

01/15/2008 
100   

01/16/2008 


Begin Construction Phase

End Construction Phase
03/18/2008 

02/27/2009 
 

 
05/12/2008 

10/07/2009 
100  05/12/2008 

10/07/2009 


Begin Closeout Phase

End Closeout Phase
02/27/2009 

08/15/2009 
 

 
10/07/2009 

08/10/2010 
100  10/07/2009 

08/10/2010 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Number of Stations / Number of Ramps Metered 66

Bond Funding Cost
Adopted:
$22,438,000
Current Approved:
$22,438,000
Actual Expenditures:
$13,993,000

 

Status as of December 31, 2023.