Traffic Detection Project |
Description: In Alameda, Contra Costa, Marin, San Mateo, Santa Clara, Solano and Sonoma Counties on various routes. Install Vehicle Detection Systems (VDS). (Prop 1B Bond Funded Project)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Alameda |
City | San Mateo, Santa Clara, Sonoma |
Zip Code | 94403, 95476 |
Senate District |
02, 03, 05, 08, 09 |
Assembly District | 01, 06, 07, 08, 11, 16, 19, 21, 27 |
Congressional District | 01, 02, 03, 06, 07, 09, 11, 12, 14 |
Caltrans District |
04 |
County/State Route | Alameda 24 |
Postmile Begin/End | 1.8 6.2 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 66 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Paul Mai | (510) 622-0754 | paul_mai@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | Paul Mai | (510) 622-0754 | paul_mai@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | Paul Mai | (510) 622-0754 | paul_mai@dot.ca.gov | |
Construction Phase |
Department of Transportation | Paul Mai | (510) 622-0754 | paul_mai@dot.ca.gov | |
Corridor System Management Plan |
Department of Transportation | Paul Mai | (510) 622-0754 | paul_mai@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SHOPP Augmentation |
$22,438 | $-19,668 | $2,770 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Total**** | $22,438 | $-19,668 | $2,770 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$1,035 | $-908 | $127 | $124 | |||
Design(PS&E) |
$1,900 | $-1,666 | $234 | $351 | |||
Right of Way |
$173 | $-152 | $21 | $0 | |||
Construction |
$19,330 | $-16,942 | $2,388 | $1,285 | |||
Total* | $22,438 | $-19,668 | $2,770 | $1,759 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
10/01/2007 |
|
10/15/2007 |
100 | 10/15/2007 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/21/2008 |
|
01/21/2008 |
100 | 01/16/2008 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
01/15/2008 |
|
01/15/2008 |
100 | 01/16/2008 |
0 0 |
Begin Construction Phase
End Construction Phase |
03/18/2008 02/27/2009 |
|
05/12/2008 10/07/2009 |
100 | 05/12/2008 10/07/2009 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
02/27/2009 08/15/2009 |
|
10/07/2009 08/10/2010 |
100 | 10/07/2009 08/10/2010 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 66 |
Bond Funding Cost | |
---|---|
Adopted: |
$22,438,000 |
Current Approved: |
$22,438,000 |
Actual Expenditures: |
$13,993,000 |
Status as of December 31, 2023.