Caltrans Logo

Traffic Detection Project

Description: In Santa Clara County, San Benito County line to San Mateo County line; also on Route 880 and in San Mateo County on Route 101. Install Vehicle Detector Systems (VDS). (Prop 1B Bond Funded Project)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Clara
City Santa Clarita
Zip Code 91350
 
Senate District
11, 13, 15
Assembly District 20, 22, 23, 24
Congressional District 15, 16
 
Caltrans District
04
 
 
County/State Route Santa Clara Var
Postmile Begin/End 0 52.6
 
County/State Route Santa Clara Var
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Number of Stations / Number of Ramps Metered  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
 
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$0 $4,822 $4,822
Non-bond Funding
State/Federal*
$0 $0 $0
Non Budgeted ETC
$0 $0 $0
 
Total**** $0 $4,822 $4,822

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$0 $216 $216 $99
Design(PS&E)
$0 $397 $397 $303
Right of Way
$0 $36 $36 $0
Construction
$0 $4,173 $4,173 $3,168
 
Total* $0 $4,822 $4,822 $3,570

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2007 

10/01/2007 
 

 
07/01/2007 

10/01/2007 
100  07/01/2007 

10/01/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2007 

11/01/2007 
 

 
07/01/2007 

10/01/2007 
100  07/01/2007 

11/26/2007 


-2 
Begin Right of Way Phase

End Right of Way Phase
10/01/2007 

12/01/2007 
 

 
10/01/2007 

10/01/2007 
95  10/01/2007 

10/24/2007 


-1 
Begin Construction Phase

End Construction Phase
04/01/2008 

02/01/2009 
 

 
04/01/2008 

12/01/2008 
04/11/2008 

09/25/2009 


-10 
Begin Closeout Phase

End Closeout Phase
10/01/2009 

10/01/2010 
 

 
10/01/2009 

10/01/2010 
25  09/25/2009 

08/10/2010 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Number of Stations / Number of Ramps Metered 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.