Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Traffic Detection Project |
Description: In Santa Clara County, San Benito County line to San Mateo County line; also on Route 880 and in San Mateo County on Route 101. Install Vehicle Detector Systems (VDS). (Prop 1B Bond Funded Project)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Clara |
City | Santa Clarita |
Zip Code | 91350 |
Senate District |
11, 13, 15 |
Assembly District | 20, 22, 23, 24 |
Congressional District | 15, 16 |
Caltrans District |
04 |
County/State Route | Santa Clara Var |
Postmile Begin/End | 0 52.6 |
County/State Route | Santa Clara Var |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
|||||
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SHOPP Augmentation |
$0 | $4,822 | $4,822 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $0 | $4,822 | $4,822 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$0 | $216 | $216 | $99 | |||
Design(PS&E) |
$0 | $397 | $397 | $303 | |||
Right of Way |
$0 | $36 | $36 | $0 | |||
Construction |
$0 | $4,173 | $4,173 | $3,168 | |||
Total* | $0 | $4,822 | $4,822 | $3,570 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/01/2007 10/01/2007 |
|
07/01/2007 10/01/2007 |
100 | 07/01/2007 10/01/2007 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2007 11/01/2007 |
|
07/01/2007 10/01/2007 |
100 | 07/01/2007 11/26/2007 |
0 -2 |
Begin Right of Way Phase
End Right of Way Phase |
10/01/2007 12/01/2007 |
|
10/01/2007 10/01/2007 |
95 | 10/01/2007 10/24/2007 |
0 -1 |
Begin Construction Phase
End Construction Phase |
04/01/2008 02/01/2009 |
|
04/01/2008 12/01/2008 |
5 | 04/11/2008 09/25/2009 |
0 -10 |
Begin Closeout Phase
End Closeout Phase |
10/01/2009 10/01/2010 |
|
10/01/2009 10/01/2010 |
25 | 09/25/2009 08/10/2010 |
0 2 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.