Traffic Detection Project |
Description: In Marin County, from San Francisco County line to Sonoma County line; also in Sonoma County at various locations. Install Vehicle Dectector Systems (VDS). (Prop 1B Bond funded project)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Marin |
City | |
Zip Code | |
Senate District |
|
Assembly District | |
Congressional District | |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 242 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
Caltrans | Wajahat Nyaz | (510) 286-5119 | wajahat.nyaz@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SHOPP Augmentation |
$0 | $7,892 | $7,892 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Total**** | $0 | $7,892 | $7,892 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$0 | $363 | $363 | $357 | |||
Design(PS&E) |
$0 | $666 | $666 | $407 | |||
Right of Way |
$0 | $61 | $61 | $0 | |||
Construction |
$0 | $6,802 | $6,802 | $4,377 | |||
Total* | $0 | $7,892 | $7,892 | $5,140 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/01/2007 10/01/2007 |
|
07/01/2007 10/01/2007 |
100 | 07/01/2007 10/01/2007 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2007 11/30/2007 |
|
07/01/2007 11/30/2007 |
100 | 07/01/2007 01/06/2008 |
0 -1 |
Begin Right of Way Phase
End Right of Way Phase |
10/01/2007 12/30/2007 |
|
10/01/2007 12/30/2007 |
100 | 10/01/2007 12/19/2007 |
0 0 |
Begin Construction Phase
End Construction Phase |
04/30/2008 02/28/2009 |
|
04/30/2008 02/28/2009 |
100 | 05/02/2008 10/19/2009 |
0 -8 |
Begin Closeout Phase
End Closeout Phase |
10/30/2009 10/01/2010 |
|
10/30/2009 10/01/2010 |
100 | 10/19/2009 09/02/2010 |
0 1 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 242 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$5,514,000 |
Actual Expenditures: |
$5,127,000 |
Status as of December 31, 2023.