Traffic Detection Project

Description: In Marin County, from San Francisco County line to Sonoma County line; also in Sonoma County at various locations. Install Vehicle Dectector Systems (VDS). (Prop 1B Bond funded project)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Marin
City
Zip Code
 
Senate District

Assembly District
Congressional District
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Number of Stations / Number of Ramps Metered  242      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Wajahat Nyaz (510) 286-5119   wajahat.nyaz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$0 $7,892 $7,892
Non-bond Funding
State/Federal*
$0 $0 $0
 
Total**** $0 $7,892 $7,892

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$0 $363 $363 $357
Design(PS&E)
$0 $666 $666 $407
Right of Way
$0 $61 $61 $0
Construction
$0 $6,802 $6,802 $4,377
 
Total* $0 $7,892 $7,892 $5,140

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2007 

10/01/2007 
 

 
07/01/2007 

10/01/2007 
100  07/01/2007 

10/01/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2007 

11/30/2007 
 

 
07/01/2007 

11/30/2007 
100  07/01/2007 

01/06/2008 


-1 
Begin Right of Way Phase

End Right of Way Phase
10/01/2007 

12/30/2007 
 

 
10/01/2007 

12/30/2007 
100  10/01/2007 

12/19/2007 


Begin Construction Phase

End Construction Phase
04/30/2008 

02/28/2009 
 

 
04/30/2008 

02/28/2009 
100  05/02/2008 

10/19/2009 


-8 
Begin Closeout Phase

End Closeout Phase
10/30/2009 

10/01/2010 
 

 
10/30/2009 

10/01/2010 
100  10/19/2009 

09/02/2010 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Number of Stations / Number of Ramps Metered 242

Bond Funding Cost
Adopted:
$0
Current Approved:
$5,514,000
Actual Expenditures:
$5,127,000

 

Status as of December 31, 2023.