Traffic Detection Project |
Description: In Solono County, from Contra Costa County line to Yolo County line; also in Napa County at various locations. Install Vehicle Dectector Systems (VDS). (Prop 1B Bond funded project)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Solano |
City | Fairfield, Napa, Vacaville |
Zip Code | 94558 |
Senate District |
02, 03, 05, 08, 09 |
Assembly District | 01, 06, 07, 08, 11, 14, 16, 19, 21, 27 |
Congressional District | 01, 02, 03, 06, 07, 09, 11, 12, 14 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 84 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Jerry Claussenius | (510) 286-5862 | jerry.claussenius@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | Jerry Claussenius | (510) 286-5862 | jerry.claussenius@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | Jerry Claussenius | (510) 286-5862 | jerry.claussenius@dot.ca.gov | |
Construction Phase |
Department of Transportation | Jerry Claussenius | (510) 286-5862 | jerry.claussenius@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SHOPP Augmentation |
$0 | $4,030 | $4,030 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Total**** | $0 | $4,030 | $4,030 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$0 | $185 | $185 | $184 | |||
Design(PS&E) |
$0 | $340 | $340 | $273 | |||
Right of Way |
$0 | $31 | $31 | $0 | |||
Construction |
$0 | $3,474 | $3,474 | $1,985 | |||
Total* | $0 | $4,030 | $4,030 | $2,442 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
100 | 10/01/2007 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
100 | 01/16/2008 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
|
|
04/01/2008 02/01/2009 |
100 | 04/23/2008 10/01/2009 |
-1 -8 |
Begin Closeout Phase
End Closeout Phase |
|
|
|
25 | 08/09/2010 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 84 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$4,030,000 |
Actual Expenditures: |
$2,615,000 |
Status as of December 31, 2023.