Caltrans Logo

Traffic Detection Project

Description: In Solono County, from Contra Costa County line to Yolo County line; also in Napa County at various locations. Install Vehicle Dectector Systems (VDS). (Prop 1B Bond funded project)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Solano
City Fairfield, Napa, Vacaville
Zip Code 94558
 
Senate District
02, 03, 05, 08, 09
Assembly District 01, 06, 07, 08, 11, 14, 16, 19, 21, 27
Congressional District 01, 02, 03, 06, 07, 09, 11, 12, 14
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Number of Stations / Number of Ramps Metered  84      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Jerry Claussenius (510) 286-5862   jerry.claussenius@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Jerry Claussenius (510) 286-5862   jerry.claussenius@dot.ca.gov
Right of Way Phase
Department of Transportation Jerry Claussenius (510) 286-5862   jerry.claussenius@dot.ca.gov
Construction Phase
Department of Transportation Jerry Claussenius (510) 286-5862   jerry.claussenius@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$0 $4,030 $4,030
Non-bond Funding
State/Federal*
$0 $0 $0
 
Total**** $0 $4,030 $4,030

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$0 $185 $185 $184
Design(PS&E)
$0 $340 $340 $273
Right of Way
$0 $31 $31 $0
Construction
$0 $3,474 $3,474 $1,985
 
Total* $0 $4,030 $4,030 $2,442

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

10/01/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
100   

01/16/2008 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

 


Begin Construction Phase

End Construction Phase
 

 
 

 
04/01/2008 

02/01/2009 
100  04/23/2008 

10/01/2009 
-1 

-8 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
25   

08/09/2010 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Number of Stations / Number of Ramps Metered 84

Bond Funding Cost
Adopted:
$0
Current Approved:
$4,030,000
Actual Expenditures:
$2,615,000

 

Status as of December 31, 2023.