Caltrans Logo

Traffic Detection Project

Description: Near Castro Valley from San Joaquin County line to Route 238. Install Vehicle Detector Systems (VDS) (Prop 1B Bond Funded Project)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City San Joaquin
Zip Code 93660
 
Senate District
07, 10
Assembly District 15, 18
Congressional District 10, 13
 
Caltrans District
04
 
 
County/State Route Alameda 580
Postmile Begin/End 0 30.8
Project Benefits
 Benefit Baseline Actual
Number of Stations / Number of Ramps Metered  53      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Cristaina Ferraz (510)286-3860   cristina.ferraz@dot.ca.gove
Design (PS&E) Phase
Department of Transportation Cristaina Ferraz (510)286-3860   cristina.ferraz@dot.ca.gove
Right of Way Phase
Department of Transportation Cristaina Ferraz (510)286-3860   cristina.ferraz@dot.ca.gove
Construction Phase
Department of Transportation Cristaina Ferraz (510)286-3860   cristina.ferraz@dot.ca.gove
 
Corridor System Management Plan
Department of Transportation Cristaina Ferraz (510)286-3860   cristina.ferraz@dot.ca.gove
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$0 $2,924 $2,924
Non-bond Funding
State/Federal*
$0 $0 $0
 
Total**** $0 $2,924 $2,924

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$0 $144 $144 $170
Design(PS&E)
$0 $264 $264 $454
Right of Way
$0 $24 $24 $0
Construction
$0 $2,492 $2,492 $1,720
 
Total* $0 $2,924 $2,924 $2,345

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

10/01/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
100   

11/26/2007 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

 


Begin Construction Phase

End Construction Phase
 

 
 

 
04/01/2008 

02/01/2009 
100  04/15/2008 

08/01/2009 


-6 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
25  10/15/2009 

08/10/2010 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Number of Stations / Number of Ramps Metered 53

Bond Funding Cost
Adopted:
$0
Current Approved:
$2,924,000
Actual Expenditures:
$2,344,000

 

Status as of December 31, 2023.