Solano 80 Roadway Rehabilitation

Description: In Solano County from Vacaville to Dixon. Rehabilitate roadway.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Solano
City Dixon, Vacaville
Zip Code 95620
 
Senate District
06
Assembly District 08
Congressional District 05
 
Caltrans District
04
 
 
County/State Route Solano 80
Postmile Begin/End 30.6 38.7
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)  62.4      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Chun Tsung 510-286-5588   chun_tsung@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Chun Tsung 510-286-5588   chun_tsung@dot.ca.gov
Right of Way Phase
Department of Transportation Chun Tsung 510-286-5588   chun_tsung@dot.ca.gov
Construction Phase
Department of Transportation Chun Tsung 510-286-5588   chun_tsung@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$38,646 $18,255 $56,901
Non-bond Funding
State/Federal*
$0 $0 $0
Non Budgeted ETC
$0 $0 $0
 
Total**** $38,646 $18,255 $56,901

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$510 $0 $510 $0
Design(PS&E)
$3,160 $-1,970 $1,190 $2,290
Right of Way
$216 $-12 $204 $1
Construction
$34,760 $20,237 $54,997 $46,760
 
Total* $38,646 $18,255 $56,901 $49,052

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/30/2009 

02/19/2010 
 

 
05/30/2009 

02/19/2010 
100  05/30/2009 

02/19/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/19/2010 

06/30/2011 
 

 
02/19/2010 

12/30/2011 
100  02/19/2010 

12/30/2011 


Begin Right of Way Phase

End Right of Way Phase
10/01/2010 

07/01/2011 
 

 
10/01/2010 

07/11/2011 
100  10/01/2010 

07/11/2011 


Begin Construction Phase

End Construction Phase
11/01/2011 

10/01/2013 
 

 
10/26/2012 

11/17/2014 
25  10/26/2012 

11/17/2014 


Begin Closeout Phase

End Closeout Phase
10/01/2013 

10/01/2014 
 

 
12/01/2014 

10/01/2016 
100  11/17/2014 

10/01/2016 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles) 62.4

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.