Caltrans Logo

Install solar-powered traffic detection devices and CCTVs.

Description: Near Carmel, from the Carmel River Bridge to the Santa Cruz County line. Install solar-powered traffic detection devices and CCTVs. (Prop 1B Bond Funded Project)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Monterey
City Carmel
Zip Code 93921
 
Senate District
05, 36
Assembly District 27, 66
Congressional District 17, 43
 
Caltrans District
05
 
 
County/State Route Monterey 1
Postmile Begin/End 72.2 102
Project Benefits
 Benefit Baseline Actual
Number of Stations / Number of Ramps Metered  3    34/29  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Doug Hessing 805-549-3386   Doug_Hessing@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Doug Hessing 805-549-3386   Doug_Hessing@dot.ca.gov
Right of Way Phase
Department of Transportation Doug Hessing 805-549-3386   Doug_Hessing@dot.ca.gov
Construction Phase
Department of Transportation Doug Hessing 805-549-3386   Doug_Hessing@dot.ca.gov
 
Corridor System Management Plan
Department of Transportation Doug Hessing 805-549-3386   Doug_Hessing@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$0 $4,904 $4,904
Non-bond Funding
State/Federal*
$0 $17 $17
 
Total**** $0 $4,921 $4,921

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$0 $364 $364 $159
Design(PS&E)
$0 $927 $927 $367
Right of Way
$0 $70 $70 $0
Construction
$0 $3,560 $3,560 $863
 
Total* $0 $4,921 $4,921 $1,389

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2007 

05/01/2008 
 

 
07/01/2007 

05/01/2008 
10/01/2007 

05/01/2008 
-3 

Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/01/2008 

04/01/2009 
 

 
05/01/2008 

04/01/2009 
05/01/2008 

08/03/2009 


-4 
Begin Right of Way Phase

End Right of Way Phase
05/01/2008 

05/01/2009 
 

 
05/01/2008 

05/01/2009 
07/31/2008 

03/12/2009 
-3 

Begin Construction Phase

End Construction Phase
10/01/2009 

05/01/2010 
 

 
10/01/2009 

05/01/2010 
03/26/2010 

06/30/2011 
-6 

-14 
Begin Closeout Phase

End Closeout Phase
12/01/2010 

06/01/2011 
 

 
12/01/2010 

06/01/2011 
75  09/01/2011 

07/16/2012 
-9 

-14 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Number of Stations / Number of Ramps Metered 3 34/29

Bond Funding Cost
Adopted:
$0
Current Approved:
$4,921,000
Actual Expenditures:
$1,376,000

 

Status as of December 31, 2023.