Install solar-powered traffic detection devices and CCTVs. |
Description: Near Carmel, from the Carmel River Bridge to the Santa Cruz County line. Install solar-powered traffic detection devices and CCTVs. (Prop 1B Bond Funded Project)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Monterey |
City | Carmel |
Zip Code | 93921 |
Senate District |
05, 36 |
Assembly District | 27, 66 |
Congressional District | 17, 43 |
Caltrans District |
05 |
County/State Route | Monterey 1 |
Postmile Begin/End | 72.2 102 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 3 | 34/29 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Doug Hessing | 805-549-3386 | Doug_Hessing@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | Doug Hessing | 805-549-3386 | Doug_Hessing@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | Doug Hessing | 805-549-3386 | Doug_Hessing@dot.ca.gov | |
Construction Phase |
Department of Transportation | Doug Hessing | 805-549-3386 | Doug_Hessing@dot.ca.gov | |
Corridor System Management Plan |
Department of Transportation | Doug Hessing | 805-549-3386 | Doug_Hessing@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SHOPP Augmentation |
$0 | $4,904 | $4,904 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $17 | $17 | ||||
Total**** | $0 | $4,921 | $4,921 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$0 | $364 | $364 | $159 | |||
Design(PS&E) |
$0 | $927 | $927 | $367 | |||
Right of Way |
$0 | $70 | $70 | $0 | |||
Construction |
$0 | $3,560 | $3,560 | $863 | |||
Total* | $0 | $4,921 | $4,921 | $1,389 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/01/2007 05/01/2008 |
|
07/01/2007 05/01/2008 |
0 | 10/01/2007 05/01/2008 |
-3 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/01/2008 04/01/2009 |
|
05/01/2008 04/01/2009 |
0 | 05/01/2008 08/03/2009 |
0 -4 |
Begin Right of Way Phase
End Right of Way Phase |
05/01/2008 05/01/2009 |
|
05/01/2008 05/01/2009 |
0 | 07/31/2008 03/12/2009 |
-3 2 |
Begin Construction Phase
End Construction Phase |
10/01/2009 05/01/2010 |
|
10/01/2009 05/01/2010 |
0 | 03/26/2010 06/30/2011 |
-6 -14 |
Begin Closeout Phase
End Closeout Phase |
12/01/2010 06/01/2011 |
|
12/01/2010 06/01/2011 |
75 | 09/01/2011 07/16/2012 |
-9 -14 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 3 | 34/29 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$4,921,000 |
Actual Expenditures: |
$1,376,000 |
Status as of December 31, 2023.