Description: Route 1 in Santa Cruz County near Watsonville, between the Santa Cruz/Monterey County line and Freedom Boulevard.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Cruz |
City | Watsonville |
Zip Code | 95019 |
Senate District |
11 |
Assembly District | 19 |
Congressional District | 14 |
Caltrans District |
05 |
County/State Route | Santa Cruz 1 |
Postmile Begin/End | 0 8.3 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 74 | 20/9 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Doug Hessing | 805-549-3386 | Doug_Hessing@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | Doug Hessing | 805-549-3386 | Doug_Hessing@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | Doug Hessing | 805-549-3386 | Doug_Hessing@dot.ca.gov | |
Construction Phase |
Department of Transportation | Doug Hessing | 805-549-3386 | Doug_Hessing@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SHOPP Augmentation |
$2,559 | $-696 | $1,863 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $8 | $8 | ||||
Total**** | $2,559 | $-688 | $1,871 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$262 | $0 | $262 | $66 | |||
Design(PS&E) |
$602 | $0 | $602 | $254 | |||
Right of Way |
$72 | $0 | $72 | $0 | |||
Construction |
$1,623 | $-688 | $935 | $584 | |||
Total* | $2,559 | $-688 | $1,871 | $904 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/01/2007 04/01/2008 |
|
07/01/2007 04/01/2008 |
100 | 07/01/2007 03/27/2008 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/01/2008 04/01/2009 |
|
04/01/2008 04/01/2009 |
100 | 04/01/2008 03/01/2009 |
0 1 |
Begin Right of Way Phase
End Right of Way Phase |
04/01/2008 02/01/2009 |
|
04/01/2008 02/01/2009 |
100 | 04/01/2008 10/01/2008 |
0 4 |
Begin Construction Phase
End Construction Phase |
07/01/2009 04/15/2010 |
|
07/01/2009 04/15/2010 |
100 | 05/11/2010 05/01/2011 |
-10 -13 |
Begin Closeout Phase
End Closeout Phase |
11/01/2010 10/01/2011 |
|
11/01/2010 10/01/2011 |
100 | 05/01/2011 04/02/2012 |
-6 -6 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 74 | 20/9 |
Bond Funding Cost | |
---|---|
Adopted: |
$2,559,000 |
Current Approved: |
$2,559,000 |
Actual Expenditures: |
$906,000 |
Status as of December 31, 2023.