Install traffic surveillance stations

Description: Near Santa Barbara and Goleta, from Garden Street to Winchester Canyon Road. Install detection only

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara
City Santa Barbara
Zip Code 93101
 
Senate District
19
Assembly District 35
Congressional District 23
 
Caltrans District
05
 
 
County/State Route Santa Barbara 101
Postmile Begin/End 13.9 27
Project Benefits
 Benefit Baseline Actual
Number of Stations / Number of Ramps Metered  21    21  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Sara von Schwind 805-549-3198   Sara_von_schwind@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Sara von Schwind 805-549-3198   Sara_von_schwind@dot.ca.gov
Right of Way Phase
Department of Transportation Sara von Schwind 805-549-3198   Sara_von_schwind@dot.ca.gov
Construction Phase
Department of Transportation Sara von Schwind 805-549-3198   Sara_von_schwind@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$2,198 $664 $2,862
Non-bond Funding
State/Federal*
$800 $-800 $0
 
Total**** $2,998 $-136 $2,862

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$390 $0 $390 $0
Design(PS&E)
$400 $0 $400 $0
Right of Way
$10 $0 $10 $0
Construction
$2,198 $-136 $2,062 $0
 
Total* $2,998 $-136 $2,862 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/2006 

04/01/2008 
 

 
10/01/2006 

04/01/2008 
100  10/01/2006 

04/01/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2008 

06/01/2008 
 

 
04/01/2008 

06/01/2008 
100  04/01/2008 

06/01/2008 


Begin Right of Way Phase

End Right of Way Phase
02/01/2008 

03/01/2008 
 

 
02/01/2008 

03/01/2008 
100  02/01/2008 

03/01/2008 


Begin Construction Phase

End Construction Phase
11/01/2008 

09/01/2009 
 

 
11/01/2008 

09/01/2009 
100  11/20/2008 

10/30/2009 
-1 

-2 
Begin Closeout Phase

End Closeout Phase
09/01/2009 

09/01/2010 
 

 
09/01/2009 

09/01/2010 
100  10/30/2009 

07/13/2010 
-2 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Number of Stations / Number of Ramps Metered 21 21

Bond Funding Cost
Adopted:
$2,198,000
Current Approved:
$2,198,000
Actual Expenditures:
$867,879

 

Status as of December 31, 2023.