Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Install traffic surveillance stations |
Description: Near Santa Barbara and Goleta, from Garden Street to Winchester Canyon Road. Install detection only
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Barbara |
City | Santa Barbara |
Zip Code | 93101 |
Senate District |
19 |
Assembly District | 35 |
Congressional District | 23 |
Caltrans District |
05 |
County/State Route | Santa Barbara 101 |
Postmile Begin/End | 13.9 27 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 21 | 21 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Sara von Schwind | 805-549-3198 | Sara_von_schwind@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | Sara von Schwind | 805-549-3198 | Sara_von_schwind@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | Sara von Schwind | 805-549-3198 | Sara_von_schwind@dot.ca.gov | |
Construction Phase |
Department of Transportation | Sara von Schwind | 805-549-3198 | Sara_von_schwind@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SHOPP Augmentation |
$2,198 | $664 | $2,862 | ||||
Non-bond Funding | |||||||
State/Federal* |
$800 | $-800 | $0 | ||||
Total**** | $2,998 | $-136 | $2,862 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$390 | $0 | $390 | $0 | |||
Design(PS&E) |
$400 | $0 | $400 | $0 | |||
Right of Way |
$10 | $0 | $10 | $0 | |||
Construction |
$2,198 | $-136 | $2,062 | $0 | |||
Total* | $2,998 | $-136 | $2,862 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
10/01/2006 04/01/2008 |
|
10/01/2006 04/01/2008 |
100 | 10/01/2006 04/01/2008 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/01/2008 06/01/2008 |
|
04/01/2008 06/01/2008 |
100 | 04/01/2008 06/01/2008 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
02/01/2008 03/01/2008 |
|
02/01/2008 03/01/2008 |
100 | 02/01/2008 03/01/2008 |
0 0 |
Begin Construction Phase
End Construction Phase |
11/01/2008 09/01/2009 |
|
11/01/2008 09/01/2009 |
100 | 11/20/2008 10/30/2009 |
-1 -2 |
Begin Closeout Phase
End Closeout Phase |
09/01/2009 09/01/2010 |
|
09/01/2009 09/01/2010 |
100 | 10/30/2009 07/13/2010 |
-2 2 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 21 | 21 |
Bond Funding Cost | |
---|---|
Adopted: |
$2,198,000 |
Current Approved: |
$2,198,000 |
Actual Expenditures: |
$867,879 |
Status as of December 31, 2023.