Install traffic surveillance stations

Description: Near Santa Barbara, from Ventura County line to Garden Street. Install detection system.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara
City Ventura
Zip Code 93003
 
Senate District
19
Assembly District 35
Congressional District 23
 
Caltrans District
05
 
 
County/State Route Santa Barbara 101
Postmile Begin/End R  0.7 13.8
Project Benefits
 Benefit Baseline Actual
Number of Stations / Number of Ramps Metered  16    16  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Sara von Schwind 805-549-3198   Sara_von_schwind@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Sara von Schwind 805-549-3198   Sara_von_schwind@dot.ca.gov
Right of Way Phase
Department of Transportation Sara von Schwind 805-549-3198   Sara_von_schwind@dot.ca.gov
Construction Phase
Department of Transportation Sara von Schwind 805-549-3198   Sara_von_schwind@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$1,899 $664 $2,563
Non-bond Funding
State/Federal*
$664 $-664 $0
 
Total**** $2,563 $0 $2,563

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$356 $0 $356 $0
Design(PS&E)
$298 $0 $298 $75
Right of Way
$10 $0 $10 $0
Construction
$1,899 $0 $1,899 $743
 
Total* $2,563 $0 $2,563 $819

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/2006 

04/01/2008 
 

 
10/01/2006 

04/01/2008 
100  10/01/2006 

04/01/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2008 

06/01/2008 
 

 
04/01/2008 

06/01/2008 
100  04/01/2008 

06/01/2008 


Begin Right of Way Phase

End Right of Way Phase
02/01/2008 

03/01/2008 
 

 
02/01/2008 

03/01/2008 
100  02/01/2008 

03/01/2008 


Begin Construction Phase

End Construction Phase
12/01/2008 

09/01/2009 
 

 
12/01/2008 

09/01/2009 
100  12/01/2008 

10/29/2009 


-2 
Begin Closeout Phase

End Closeout Phase
09/01/2009 

09/01/2010 
 

 
09/01/2009 

09/01/2010 
100  10/30/2009 

09/02/2010 
-2 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Number of Stations / Number of Ramps Metered 16 16

Bond Funding Cost
Adopted:
$1,899,000
Current Approved:
$1,899,000
Actual Expenditures:
$743,136

 

Status as of December 31, 2023.