Install traffic surveillance stations |
Description: In Santa Cruz County from the Freedom Boulevard overcrossing near Aptos to the Ocean Street overcrossing in Santa Cruz. Install traffic detection system.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Cruz |
City | Santa Cruz |
Zip Code | 95064 |
Senate District |
11 |
Assembly District | 27 |
Congressional District | 17 |
Caltrans District |
05 |
County/State Route | Santa Cruz 1 |
Postmile Begin/End | 8 17.5 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 29 | 16 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Luis Duazo | 805 542-4678 | luis_duazo@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Ernie Penuna | 559 230-3142 | ernie_penuna@dot.ca.gov | |
Right of Way Phase |
Caltrans | Connie Shellooe | 805 549-3471 | connie_shellooe@dot.ca.gov | |
Construction Phase |
Caltrans | Siobhan Saunders | 831 427-4857 | siobhan_saunders@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SHOPP Augmentation |
$1,781 | $0 | $1,781 | ||||
Non-bond Funding | |||||||
State/Federal* |
$699 | $0 | $699 | ||||
Total**** | $2,480 | $0 | $2,480 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$376 | $0 | $376 | $238 | |||
Design(PS&E) |
$312 | $0 | $312 | $196 | |||
Right of Way |
$11 | $0 | $11 | $0 | |||
Construction |
$1,781 | $0 | $1,781 | $918 | |||
Total* | $2,480 | $0 | $2,480 | $1,351 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
10/01/2006 04/01/2008 |
|
10/01/2006 04/01/2008 |
100 | 10/01/2006 04/01/2008 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/01/2007 05/01/2008 |
|
06/01/2007 05/01/2008 |
100 | 06/01/2007 05/01/2008 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
01/01/2008 03/01/2008 |
|
01/01/2008 03/01/2008 |
100 | 01/01/2008 03/01/2008 |
0 0 |
Begin Construction Phase
End Construction Phase |
12/01/2008 09/01/2009 |
|
12/01/2008 09/01/2009 |
100 | 12/03/2008 12/30/2009 |
0 -4 |
Begin Closeout Phase
End Closeout Phase |
09/01/2009 09/01/2010 |
|
09/01/2009 09/01/2010 |
50 | 11/01/2009 07/21/2010 |
-2 1 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 29 | 16 |
Bond Funding Cost | |
---|---|
Adopted: |
$1,781,000 |
Current Approved: |
$1,781,000 |
Actual Expenditures: |
$975,289 |
Status as of December 31, 2023.