Install traffic surveillance stations

Description: In Santa Cruz County from the Freedom Boulevard overcrossing near Aptos to the Ocean Street overcrossing in Santa Cruz. Install traffic detection system.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Cruz
City Santa Cruz
Zip Code 95064
 
Senate District
11
Assembly District 27
Congressional District 17
 
Caltrans District
05
 
 
County/State Route Santa Cruz 1
Postmile Begin/End 8 17.5
Project Benefits
 Benefit Baseline Actual
Number of Stations / Number of Ramps Metered  29    16  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Luis Duazo 805 542-4678   luis_duazo@dot.ca.gov
Design (PS&E) Phase
Caltrans Ernie Penuna 559 230-3142   ernie_penuna@dot.ca.gov
Right of Way Phase
Caltrans Connie Shellooe 805 549-3471   connie_shellooe@dot.ca.gov
Construction Phase
Caltrans Siobhan Saunders 831 427-4857   siobhan_saunders@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$1,781 $0 $1,781
Non-bond Funding
State/Federal*
$699 $0 $699
 
Total**** $2,480 $0 $2,480

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$376 $0 $376 $238
Design(PS&E)
$312 $0 $312 $196
Right of Way
$11 $0 $11 $0
Construction
$1,781 $0 $1,781 $918
 
Total* $2,480 $0 $2,480 $1,351

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/2006 

04/01/2008 
 

 
10/01/2006 

04/01/2008 
100  10/01/2006 

04/01/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2007 

05/01/2008 
 

 
06/01/2007 

05/01/2008 
100  06/01/2007 

05/01/2008 


Begin Right of Way Phase

End Right of Way Phase
01/01/2008 

03/01/2008 
 

 
01/01/2008 

03/01/2008 
100  01/01/2008 

03/01/2008 


Begin Construction Phase

End Construction Phase
12/01/2008 

09/01/2009 
 

 
12/01/2008 

09/01/2009 
100  12/03/2008 

12/30/2009 


-4 
Begin Closeout Phase

End Closeout Phase
09/01/2009 

09/01/2010 
 

 
09/01/2009 

09/01/2010 
50  11/01/2009 

07/21/2010 
-2 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Number of Stations / Number of Ramps Metered 29 16

Bond Funding Cost
Adopted:
$1,781,000
Current Approved:
$1,781,000
Actual Expenditures:
$975,289

 

Status as of December 31, 2023.