Mid City/Expo LRT Project Phase 1 |
|
Description: Expand LR 7.7 miles
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Los Angeles |
| City | Los Angeles |
| Zip Code | 90012 |
| Senate District |
22, 26 |
| Assembly District | 46, 47, 48 |
| Congressional District | 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 42, 43, 44, 45, 46 |
| Caltrans District |
07 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increased Ridership | 14 | 14 |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
LA County Metropolitan Transportation Authority | Gladys Lowe | (213) 922-2459 | loweg@metro.net |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-99313 |
$53,500 | $27,970 | $81,470 | ||||
| PTMISEA-99314 |
$0 | $56,993 | $56,993 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$643,900 | $-63,372 | $580,528 | ||||
| Local** |
$0 | $131,697 | $131,697 | ||||
| Total**** | $697,400 | $153,288 | $850,688 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$23,402 | $36 | $23,438 | $23,438 | $23,438 | $-0 | |
| Design(PS&E) |
$16,700 | $0 | $16,700 | $16,834 | $16,834 | $-134 | |
| Right of Way |
$24,947 | $-10,247 | $14,700 | $6,959 | $6,959 | $7,741 | |
| Construction |
$632,351 | $163,499 | $795,850 | $442,143 | $442,143 | $353,707 | |
| Total* | $697,400 | $153,288 | $850,688 | $489,375 | $489,375 | $361,313 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
05/01/2000 02/01/2006 |
|
05/01/2000 02/01/2006 |
100 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/01/2006 12/01/2009 |
|
02/01/2006 12/01/2009 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
02/01/2006 02/01/2010 |
01/04/2013 |
02/01/2006 06/01/2013 |
99 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
02/01/2006 09/01/2012 |
01/04/2013 |
02/01/2006 06/01/2013 |
99 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
11/01/2012 01/01/2013 |
01/04/2013 01/04/2013 |
06/01/2013 09/01/2013 |
0 | |
0 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increased Ridership | 14 | 14 |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$53,500,000 |
| Current Approved: |
$138,462,779 |
| Actual Expenditures: |
$138,462,779 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31