Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Mid City/Expo LRT Project Phase 2 |
|
Description: Expand Light Rail - Expo Line
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Los Angeles |
| City | Los Angeles |
| Zip Code | 90012 |
| Senate District |
23, 26, 28 |
| Assembly District | 41, 47, 53 |
| Congressional District | 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 42, 43, 44, 45, 46 |
| Caltrans District |
07 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Additonal Rail Miles | 7 | |
| Increased Ridership | 3 | 103 |
| Useful Life (years) | 30 | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
LA County Metropolitan Transportation Authority | Gladys Lowe | (213) 922-2459 | loweg@metro.net |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-99313 |
$0 | $60,993 | $60,993 | ||||
| PTMISEA-99314 |
$0 | $74,990 | $74,990 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$0 | $76,059 | $76,059 | ||||
| Local** |
$0 | $874,374 | $874,374 | ||||
| Total**** | $0 | $1,086,417 | $1,086,417 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $19,989 | $19,989 | $13,602 | $13,602 | $6,387 | |
| Design(PS&E) |
$0 | $3,713 | $3,713 | $18,760 | $18,760 | $-15,046 | |
| Right of Way |
$0 | $253,701 | $253,701 | $124,932 | $124,932 | $128,769 | |
| Construction |
$0 | $809,013 | $809,013 | $928,023 | $928,023 | $-119,010 | |
| Total* | $0 | $1,086,417 | $1,086,417 | $1,085,317 | $1,085,317 | $1,100 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
01/01/2007 12/01/2010 |
03/10/2011 |
01/01/2007 01/01/2010 |
100 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/01/2010 07/01/2015 |
03/10/2011 09/04/2018 |
02/01/2010 10/01/2010 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
12/01/2010 07/01/2013 |
03/10/2011 |
02/01/2010 07/01/2013 |
100 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
07/01/2010 07/01/2015 |
09/04/2018 09/04/2018 |
03/01/2010 11/01/2015 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
07/01/2015 07/01/2018 |
09/04/2018 09/04/2018 |
02/01/2017 06/01/2019 |
100 | |
0 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Additonal Rail Miles | 7 | |
| Increased Ridership | 3 | 103 |
| Useful Life (years) | 30 | |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$0 |
| Current Approved: |
$135,983,130 |
| Actual Expenditures: |
$135,983,130 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31
