Description: Purchase 95 CNG articulated buses
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Los Angeles |
| City | Los Angeles |
| Zip Code | 90012 |
| Senate District |
17, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 32 |
| Assembly District | 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61 |
| Congressional District | 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 42, 43, 44, 45, 46 |
| Caltrans District |
07 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increased Ridership | 50 | 50 |
| Reduce Emissions (percent) | ||
| Useful Life (years) | 12 | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
LA County Metropolitan Transportation Authority | Emma Nogales | (213) 922-3066 | nogalese@metro.net |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-99314 |
$50,000 | $-757 | $49,243 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$36,427 | $-2,428 | $34,000 | ||||
| Local** |
$0 | $2,428 | $2,428 | ||||
| Total**** | $86,427 | $-756 | $85,671 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$86,427 | $-756 | $85,671 | $85,671 | $85,671 | $0 | |
| Total* | $86,427 | $-756 | $85,671 | $85,671 | $85,671 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
05/15/2007 06/30/2009 |
08/28/2009 |
05/15/2007 03/07/2008 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
09/30/2009 12/31/2009 |
06/17/2010 06/17/2010 |
09/01/2010 09/30/2010 |
0 | |
0 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increased Ridership | 50 | 50 |
| Reduce Emissions (percent) | ||
| Useful Life (years) | 12 | |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$50,000,000 |
| Current Approved: |
$49,243,467 |
| Actual Expenditures: |
$49,243,467 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31