Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
New Bus Operations & Maintenance Facility (Division 13) |
|
Description: Construction of a New Bus Operations & Maintenance Facility (Union Division)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Los Angeles |
| City | Los Angeles |
| Zip Code | 90012 |
| Senate District |
22 |
| Assembly District | 46 |
| Congressional District | 34 |
| Caltrans District |
07 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 8 | |
| Reduced Operating/Maintenance Cost | 10 | |
| Useful Life (years) | 30 | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
LA County Metropolitan Transportation Authority | Nela De Castro | (213) 922-6166 | Decastrom@metro.net |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-Interest |
$0 | $14 | $14 | ||||
| PTMISEA-99313 |
$4,454 | $40,669 | $45,123 | ||||
| PTMISEA-99314 |
$539 | $7,103 | $7,642 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$0 | $53,250 | $53,250 | ||||
| Local** |
$1,900 | $12,427 | $14,327 | ||||
| Total**** | $6,893 | $113,463 | $120,356 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$4,900 | $-4,397 | $503 | $302 | $302 | $201 | |
| Design(PS&E) |
$514 | $10,925 | $11,439 | $8,619 | $8,619 | $2,820 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$68,786 | $39,628 | $108,414 | $43,843 | $43,843 | $64,570 | |
| Total* | $6,893 | $113,463 | $120,356 | $52,765 | $52,765 | $67,591 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
09/01/2006 09/30/2008 |
08/28/2009 09/03/2010 |
09/01/2006 09/01/2010 |
100 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/01/2008 01/01/2010 |
08/28/2009 03/10/2011 |
12/01/2008 10/01/2010 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
06/01/2010 12/31/2011 |
03/08/2012 09/04/2014 |
03/01/2010 05/01/2015 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
01/01/2012 08/30/2012 |
03/01/2017 03/01/2017 |
02/01/2017 02/28/2017 |
100 | |
0 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 8 | |
| Reduced Operating/Maintenance Cost | 10 | |
| Useful Life (years) | 30 | |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$4,992,816 |
| Current Approved: |
$52,764,816 |
| Actual Expenditures: |
$52,764,816 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31
